11466 W VALERIO ST 91605

Certificate Information: 11466 W VALERIO ST 91605

Application / Permit
20016-20000-20179
Plan Check / Job No.
B20VN10714
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DETACHED 2-CAR GARAGE TO ADU AND ADD 5' 5" X 20' 5" STORAGE/LAUNDRY TO ADU. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 2/8/2021
Issuing Office
Current Status
CofO Issued on 8/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 GURUNATH NESARAJAH
Corrections Issued 8/22/2020 GURUNATH NESARAJAH
Building Plans Picked Up 8/26/2020 APPLICANT
Plan Check Approved 1/11/2021 GURUNATH NESARAJAH
Issued 2/8/2021 APPLICANT
CofO in Progress 8/4/2021 DANIEL DREW
Permit Finaled 8/13/2022 DANIEL ORRANTE
CofO Issued 8/13/2022 DANIEL ORRANTE
Permit Finaled 8/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/30/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 10/30/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/2/2020 ADRIAN CASTRO
Sewer availability Cleared 11/2/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/16/2021 Approved DANIEL DREW
PLUMBING-Rough 2/16/2021 Partial Approval DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 3/2/2021 Not Ready for Inspection DANIEL DREW
Sewer 3/2/2021 Approved DANIEL DREW
Underground Mechanical 3/2/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 3/5/2021 Partial Approval DANIEL DREW
Rough-Elec/Plmb/HVAC 3/5/2021 Not Ready for Inspection DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Partial Approval DANIEL DREW
Green Building Rough 3/10/2021 Not Ready for Inspection DANIEL DREW
Rough-Elec/Plmb/HVAC 3/10/2021 Partial Approval DANIEL DREW
BUILDING-Rough-Frame 3/19/2021 Approved DANIEL DREW
Green Building Rough 3/19/2021 Approved DANIEL DREW
Interior/Exterior Lathing 3/19/2021 Approved DANIEL DREW
Shower Pan 3/19/2021 Approved DANIEL DREW
Insulation 3/22/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 3/22/2021 Approved CHARLES POWELL
Drywall Nailing 3/25/2021 Approved DANIEL DREW
Drywall Nailing 3/26/2021 Approved DANIEL DREW
ELECTRICAL-Final 4/12/2021 Corrections Issued DANIEL DREW
SGSOV-Seismic Gas S/O Valve 4/15/2021 SGSOV Not Ready ARAM AVEDISIAN
ELECTRICAL-Final 4/22/2021 Approved DANIEL DREW
Final 4/22/2021 Not Ready for Inspection DANIEL DREW
Green Building Final 4/22/2021 Corrections Issued DANIEL DREW
HVAC-Final 4/22/2021 Approved DANIEL DREW
PLUMBING-Final 4/22/2021 Approved DANIEL DREW
Smoke Detectors 4/22/2021 Approved DANIEL DREW
Final 5/12/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/12/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/12/2021 SGSOV Approved JENNIFER RABUCHIN
Final 6/29/2021 Not Ready for Inspection DANIEL DREW
Green Building Final 6/29/2021 Not Ready for Inspection DANIEL DREW
Final 8/3/2021 OK to Issue CofO DANIEL DREW
Green Building Final 8/3/2021 Approved DANIEL DREW