5161 N NESTLE AVE 91356

Certificate Information: 5161 N NESTLE AVE 91356

Application / Permit
20016-20000-19986
Plan Check / Job No.
B20VN10633
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) GARAGE INTO A (N) LIVING ROOM AND ADD NEW CARPORT. INTERIOR REMODEL TO (E) SFD. ALL WORK PER ENGINEER. NFPA-13D FIRE SPRINKLER THRU-OUT.
Permit Issued
Issued on 4/8/2021
Issuing Office
Current Status
Issued on 4/8/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/10/2020 APPLICANT
Assigned to Plan Check Engineer 9/11/2020 PINANK PATEL
Corrections Issued 9/11/2020 PINANK PATEL
Applicant returned to address corrections 11/25/2020 PINANK PATEL
Applicant returned to address corrections 3/1/2021 PINANK PATEL
Plan Check Approved 3/9/2021 PINANK PATEL
Issued 4/8/2021 APPLICANT
Building Plans Picked Up 4/12/2021 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/20/2020 BRIAN MILLER
Low Impact Development Cleared 2/10/2021 JORGE MEJIA LEMUS
Hydrant and Access approval Cleared 2/23/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 2/23/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/2/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/9/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/14/2021 Approved DAVID SANDOVAL
Footing/Foundation/Slab 4/30/2021 Partial Inspection RONALD COWAN
Excavation/Setback/Form/Re-Bar 5/21/2021 Approved RONALD COWAN
Footing/Foundation/Slab 5/21/2021 Approved RONALD COWAN
PLUMBING-Rough 5/28/2021 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 7/26/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 8/30/2021 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 8/30/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 8/30/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 8/30/2021 Approved CHRISTOPHER DELLEFIELD
Verify Sprinkler Sign Off 8/30/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/14/2021 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 9/14/2021 Approved DAVID SANDOVAL
Green Building Rough 9/14/2021 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 10/5/2021 Partial Approval DAVID SANDOVAL
Green Building Rough 10/5/2021 Partial Approval DAVID SANDOVAL
Interior/Exterior Lathing 10/5/2021 Partial Approval DAVID SANDOVAL
Shower Pan 10/5/2021 Approved DAVID SANDOVAL
Drywall Nailing 10/26/2021 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 11/3/2021 Approved DAVID SANDOVAL
Green Building Rough 11/3/2021 Approved DAVID SANDOVAL
Interior/Exterior Lathing 11/3/2021 Approved DAVID SANDOVAL
Final 1/24/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 1/24/2022 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 1/24/2022 SGSOV Approved DAVID SANDOVAL
Smoke Detectors 1/24/2022 Approved DAVID SANDOVAL
ELECTRICAL-Final 2/15/2022 Approved DAVID SANDOVAL
Final 2/15/2022 Partial Approval DAVID SANDOVAL
Green Building Final 2/15/2022 Approved DAVID SANDOVAL
HVAC-Final 2/15/2022 Approved DAVID SANDOVAL
PLUMBING-Final 2/15/2022 Approved DAVID SANDOVAL