6915 N LINDLEY AVE 91335
Certificate Information: 6915 N LINDLEY AVE 91335
- Application / Permit
- 20016-20000-19964
- Plan Check / Job No.
- B20VN10621
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19' 6" X 19' 5" DETACHED GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 9/29/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 8/22/2020 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 8/25/2020 | APPLICANT |
| Plan Check Approved | 9/15/2020 | GURUNATH NESARAJAH |
| Issued | 9/29/2020 | APPLICANT |
| CofO in Progress | 9/15/2021 | VINCENT HANLEY |
| Permit Finaled | 9/17/2021 | JOHN JANSON |
| CofO Issued | 9/17/2021 | JOHN JANSON |
| Permit Finaled | 9/17/2021 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 8/27/2020 | MIGUEL GAMBOA |
| Address approval | Cleared | 8/31/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/31/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/1/2021 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 3/3/2021 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/3/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/16/2021 | Approved | VINCENT HANLEY |
| Insulation | 4/16/2021 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 4/16/2021 | Approved | VINCENT HANLEY |
| Insulation | 4/23/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/29/2021 | No Access for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 6/15/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/15/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/15/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/15/2021 | Approved | VINCENT HANLEY |
| Shower Pan | 6/15/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/15/2021 | Approved | VINCENT HANLEY |
| Final | 9/15/2021 | OK to Issue CofO | VINCENT HANLEY |
| Gas Test | 9/15/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 9/15/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 9/15/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/15/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/15/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 9/15/2021 | Approved | VINCENT HANLEY |