458 N KILKEA DR 90048

Certificate Information: 458 N KILKEA DR 90048

Application / Permit
20016-20000-19961
Plan Check / Job No.
B20VN10619
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR INTERIOR REMODEL TO (E) 2-STORY SFD; ADDITION OF ENTRY AT SIDE OF (E) SFD (9'-8 5/8" X 2'-1 5/8")
Permit Issued
Issued on 1/20/2021
Issuing Office
Current Status
CofO Issued on 3/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 NILOOFAR MEHRAIN
Corrections Issued 9/29/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 9/30/2020 APPLICANT
Applicant returned to address corrections 10/29/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 11/4/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/8/2020 NILOOFAR MEHRAIN
Plan Check Approved 12/8/2020 NILOOFAR MEHRAIN
Issued 1/20/2021 APPLICANT
CofO in Progress 2/8/2022 CHRIS CHRISTENSEN
Permit Finaled 3/2/2022 DEROLD HAUFF
Permit Finaled 3/2/2022 DEROLD HAUFF
CofO Issued 3/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 10/14/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 10/20/2020 JUAN ASHTON

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 2/10/2021 Conditional Approval CHRIS CHRISTENSEN
Deputy Wood Construction 4/1/2021 No Access for Inspection ELMER BLAND
Deputy Wood Construction 4/7/2021 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/12/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 4/12/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 4/12/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 4/12/2021 Partial Approval CHRIS CHRISTENSEN
Wood Frame 4/12/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/16/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 4/16/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 4/27/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/27/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 5/27/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 5/27/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 5/27/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 5/27/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/8/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/8/2021 Approved CHRIS CHRISTENSEN
Gas Test 6/8/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 6/8/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 6/8/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/8/2021 Approved CHRIS CHRISTENSEN
Shower Pan 6/8/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 6/8/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/15/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 6/15/2021 Approved CHRIS CHRISTENSEN
Shower Pan 6/15/2021 Approved CHRIS CHRISTENSEN
Insulation 6/23/2021 Approved JESUS PINEDA
Interior/Exterior Lathing 6/23/2021 Partial Approval JESUS PINEDA
Interior/Exterior Lathing 6/29/2021 Approved THOMAS LOGRASSO
Drywall Nailing 7/12/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 12/21/2021 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Final 1/12/2022 Corrections Issued CHRIS CHRISTENSEN
Gas Test 1/12/2022 Approved CHRIS CHRISTENSEN
HVAC-Final 1/12/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Final 1/12/2022 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Final 2/7/2022 Approved CHRIS CHRISTENSEN
Final 2/7/2022 OK to Issue CofO CHRIS CHRISTENSEN
Footing/Foundation/Slab 2/7/2022 Approved CHRIS CHRISTENSEN
Green Building Final 2/7/2022 Approved CHRIS CHRISTENSEN
HVAC-Final 2/7/2022 Approved CHRIS CHRISTENSEN
METHANE-Barrier 2/7/2022 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 2/7/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 2/7/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/7/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 2/7/2022 Approved CHRIS CHRISTENSEN