458 N KILKEA DR 90048
Certificate Information: 458 N KILKEA DR 90048
- Application / Permit
- 20016-20000-19961
- Plan Check / Job No.
- B20VN10619
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INTERIOR REMODEL TO (E) 2-STORY SFD; ADDITION OF ENTRY AT SIDE OF (E) SFD (9'-8 5/8" X 2'-1 5/8")
- Permit Issued
- Issued on 1/20/2021
- Issuing Office
- Current Status
- CofO Issued on 3/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/29/2020 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 9/30/2020 | APPLICANT |
| Applicant returned to address corrections | 10/29/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 11/4/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 12/8/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/8/2020 | NILOOFAR MEHRAIN |
| Issued | 1/20/2021 | APPLICANT |
| CofO in Progress | 2/8/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 3/2/2022 | DEROLD HAUFF |
| Permit Finaled | 3/2/2022 | DEROLD HAUFF |
| CofO Issued | 3/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/14/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2020 | JUAN ASHTON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 2/10/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 4/1/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Wood Construction | 4/7/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/12/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 4/12/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 4/12/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 4/12/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 4/12/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 4/16/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/16/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 4/27/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/27/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 5/27/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 5/27/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/27/2021 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 5/27/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/8/2021 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 6/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 6/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/8/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/8/2021 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 6/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 6/8/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/15/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 6/15/2021 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 6/15/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 6/23/2021 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/23/2021 | Partial Approval | JESUS PINEDA |
| Interior/Exterior Lathing | 6/29/2021 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 7/12/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 12/21/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 1/12/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Gas Test | 1/12/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 1/12/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Final | 1/12/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 2/7/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 2/7/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 2/7/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 2/7/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 2/7/2022 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 2/7/2022 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 2/7/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 2/7/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 2/7/2022 | Approved | CHRIS CHRISTENSEN |