747 W OXFORD AVE 90292

Certificate Information: 747 W OXFORD AVE 90292

Application / Permit
20016-20000-19953
Plan Check / Job No.
B20VN10613
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO THE (E) SFD. NEW SKYLIGHTS.
Permit Issued
Issued on 12/18/2020
Issuing Office
Current Status
Permit Finaled on 3/17/2021

Permit Application Status History

Submitted 8/27/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 RICARDO RAMIREZ
Corrections Issued 9/4/2020 RICARDO RAMIREZ
Applicant returned to address corrections 10/16/2020 PARISA ZAHABI
Applicant returned to address corrections 11/5/2020 PARISA ZAHABI
Plan Check Approved 11/28/2020 PARISA ZAHABI
Issued 12/18/2020 APPLICANT
Permit Finaled 3/17/2021 DAVID HEINE

Permit Application Clearance Information

Miscellaneous Cleared 9/28/2020 PABLO ESTRADA
Miscellaneous Cleared 9/28/2020 PABLO ESTRADA
Coastal Zone Cleared 9/30/2020 PABLO ESTRADA
Specific Plan Cleared 10/7/2020 BINDU KANNAN
Specific Plan Cleared 10/7/2020 BINDU KANNAN
ZI Cleared 10/7/2020 BINDU KANNAN
ZI Cleared 10/7/2020 BINDU KANNAN

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/29/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/31/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/25/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 1/25/2021 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 1/25/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 1/25/2021 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 1/26/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 1/26/2021 Approved ENRIQUE MIRELES
HVAC-Rough 1/26/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/26/2021 Approved ENRIQUE MIRELES
Insulation 1/27/2021 Approved ENRIQUE MIRELES
Shower Pan 1/28/2021 Approved ENRIQUE MIRELES
Drywall Nailing 2/1/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/2/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/15/2021 Approved JOHNNY MIRANDA
Final 3/15/2021 Corrections Issued JOHNNY MIRANDA
HVAC-Final 3/15/2021 Approved JOHNNY MIRANDA
PLUMBING-Final 3/15/2021 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 3/15/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Final 3/17/2021 Approved DAVID HEINE
Final 3/17/2021 Permit Finaled DAVID HEINE
HVAC-Final 3/17/2021 Approved DAVID HEINE
PLUMBING-Final 3/17/2021 Approved DAVID HEINE