17043-17045 W CANTARA ST 91406
Certificate Information: 17043-17045 W CANTARA ST 91406
- Application / Permit
- 20016-20000-19873
- Plan Check / Job No.
- B20VN10577
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) AND ENCLOSE THE (E) ATTACHED REAR PATIO
- Permit Issued
- Issued on 10/15/2020
- Issuing Office
- Current Status
- CofO Issued on 4/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | SELLA BENYAMIN |
| Corrections Issued | 8/24/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 8/25/2020 | APPLICANT |
| Plan Check Approved | 10/1/2020 | SELLA BENYAMIN |
| Issued | 10/15/2020 | APPLICANT |
| CofO in Progress | 3/19/2021 | MICHAEL TEMPLE |
| CofO in Progress | 3/19/2021 | MICHAEL TEMPLE |
| CofO in Progress | 3/19/2021 | MICHAEL TEMPLE |
| CofO Issued | 4/17/2021 | MICHAEL SMITH |
| Permit Finaled | 4/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/14/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/21/2020 | Not Ready for Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 10/27/2020 | Not Ready for Inspection | DANIEL ORRANTE |
| Footing/Foundation/Slab | 10/27/2020 | Approved | DANIEL ORRANTE |
| Green Building Rough | 10/27/2020 | Not Ready for Inspection | DANIEL ORRANTE |
| PLUMBING-Rough | 10/27/2020 | Partial Approval | DANIEL ORRANTE |
| ELECTRICAL-Rough | 11/4/2020 | Approved | ARTHUR SARGSYAN |
| Insulation | 11/4/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 11/12/2020 | Partial Approval | ARTHUR SARGSYAN |
| Green Building Rough | 11/12/2020 | Partial Approval | ARTHUR SARGSYAN |
| Insulation | 11/12/2020 | Partial Approval | ARTHUR SARGSYAN |
| Shower Pan | 11/12/2020 | Partial Approval | ARTHUR SARGSYAN |
| Drywall Nailing | 11/17/2020 | Corrections Issued | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 11/17/2020 | Corrections Issued | MICHAEL TEMPLE |
| Special/Order Compliance | 11/18/2020 | Corrections Issued | ARTHUR SARGSYAN |
| Special/Order Compliance | 11/18/2020 | Partial Inspection | MICHAEL TEMPLE |
| Pre-Inspection | 11/19/2020 | Partial Inspection | ARTHUR SARGSYAN |
| Drywall Nailing | 11/23/2020 | Partial Inspection | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 11/23/2020 | Partial Inspection | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 1/13/2021 | Approved | ARTHUR SARGSYAN |
| Final | 1/13/2021 | Partial Inspection | ARTHUR SARGSYAN |
| Green Building Final | 1/13/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 1/13/2021 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 1/13/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 1/13/2021 | Approved | ARTHUR SARGSYAN |
| Final | 2/24/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Final | 3/19/2021 | OK to Issue CofO | MICHAEL TEMPLE |