14746 W COHASSET ST 91405
Certificate Information: 14746 W COHASSET ST 91405
- Application / Permit
- 20016-20000-19805
- Plan Check / Job No.
- B20VN10532
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) REC. ROOM AND A PORTION OF THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 9/30/2020
- Issuing Office
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2020 | ADAM HEGAZI |
| Corrections Issued | 8/19/2020 | ADAM HEGAZI |
| Plan Check Approved | 9/15/2020 | RICHARD GARCIA |
| Issued | 9/30/2020 | APPLICANT |
| CofO in Progress | 8/25/2021 | GREGG CUMMINGS |
| CofO Issued | 9/25/2021 | MICHAEL SMITH |
| Permit Finaled | 9/25/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/27/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/15/2021 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 1/22/2021 | Partial Inspection | GREGG CUMMINGS |
| Sewer | 1/22/2021 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 1/22/2021 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/18/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 2/18/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 2/18/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 2/18/2021 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 7/9/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 8/20/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 8/20/2021 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/20/2021 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 8/20/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/25/2021 | Approved | GREGG CUMMINGS |
| Final | 8/25/2021 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 8/25/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 8/25/2021 | Approved | GREGG CUMMINGS |