7745-7747 N SEDAN AVE 91304

Certificate Information: 7745-7747 N SEDAN AVE 91304

Application / Permit
20016-20000-19688
Plan Check / Job No.
B20VN10485
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CGS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/19/2021
Issuing Office
Current Status
CofO Issued on 8/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2020 APPLICANT
Assigned to Plan Check Engineer 8/19/2020 ADAM HEGAZI
Corrections Issued 8/19/2020 ADAM HEGAZI
Applicant returned to address corrections 9/20/2020 RICHARD GARCIA
Applicant returned to address corrections 11/5/2020 OMAR GARNICA
Plan Check Approved 5/10/2021 OMAR GARNICA
Issued 5/19/2021 APPLICANT
Building Plans Picked Up 6/11/2021 APPLICANT
CofO in Progress 7/27/2022 CHRIS CHRISTENSEN
Permit Finaled 8/2/2022 JOHN JANSON
CofO Issued 8/2/2022 JOHN JANSON
Permit Finaled 8/2/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/3/2020 GUILLERMO PETRA
Sewer availability Cleared 9/3/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 9/9/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/30/2021 Conditional Approval DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 10/6/2021 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 10/6/2021 Not Ready for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 3/4/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 3/25/2022 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/25/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 3/25/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 3/25/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/1/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 4/1/2022 Approved CHRIS CHRISTENSEN
Pre-Inspection 4/1/2022 Corrections Issued CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/8/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 4/8/2022 Conditional Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/8/2022 Partial Approval CHRIS CHRISTENSEN
Insulation 4/13/2022 Conditional Approval JESUS PINEDA
Drywall Nailing 4/19/2022 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 4/19/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 4/22/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 4/22/2022 Approved JUSTIN HAWLEY
Shower Pan 4/22/2022 Approved JUSTIN HAWLEY
Final 7/21/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 7/21/2022 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/21/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 7/21/2022 Approved CHRIS CHRISTENSEN
Final 7/26/2022 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 7/26/2022 Approved CHRIS CHRISTENSEN
Service/Power Release 7/26/2022 Approved CHRIS CHRISTENSEN