7745-7747 N SEDAN AVE 91304
Certificate Information: 7745-7747 N SEDAN AVE 91304
- Application / Permit
- 20016-20000-19688
- Plan Check / Job No.
- B20VN10485
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CGS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2020 | ADAM HEGAZI |
| Corrections Issued | 8/19/2020 | ADAM HEGAZI |
| Applicant returned to address corrections | 9/20/2020 | RICHARD GARCIA |
| Applicant returned to address corrections | 11/5/2020 | OMAR GARNICA |
| Plan Check Approved | 5/10/2021 | OMAR GARNICA |
| Issued | 5/19/2021 | APPLICANT |
| Building Plans Picked Up | 6/11/2021 | APPLICANT |
| CofO in Progress | 7/27/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 8/2/2022 | JOHN JANSON |
| CofO Issued | 8/2/2022 | JOHN JANSON |
| Permit Finaled | 8/2/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/3/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 9/3/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/30/2021 | Conditional Approval | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 10/6/2021 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 10/6/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 3/4/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 3/25/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/25/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 3/25/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/25/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 4/1/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/1/2022 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 4/1/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/8/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/8/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/8/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 4/13/2022 | Conditional Approval | JESUS PINEDA |
| Drywall Nailing | 4/19/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/19/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 4/22/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 4/22/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 4/22/2022 | Approved | JUSTIN HAWLEY |
| Final | 7/21/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 7/21/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 7/21/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 7/26/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 7/26/2022 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 7/26/2022 | Approved | CHRIS CHRISTENSEN |