Permit Issued
Issued on 11/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2020 APPLICANT
Assigned to Plan Check Engineer 8/19/2020 JENNIFER LEE
Corrections Issued 8/20/2020 JENNIFER LEE
Applicant returned to address corrections 9/29/2020 JENNIFER LEE
Applicant returned to address corrections 10/19/2020 JENNIFER LEE
Plan Check Approved 11/13/2020 JEROME MAGAT PALMA
Issued 11/17/2020 APPLICANT
CofO in Progress 3/30/2022 RAUL OLAGI
Permit Finaled 6/11/2022 MICHAEL SMITH
CofO Issued 6/11/2022 MICHAEL SMITH
Permit Finaled 6/11/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/24/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 8/24/2020 BRIAN MILLER
Sewer availability Cleared 8/24/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/2/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/8/2021 Not Ready for Inspection DAVID SCANTLIN
Masonry Wall/Backfill 3/8/2021 Not Ready for Inspection DAVID SCANTLIN
Footing/Foundation/Slab 3/23/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 6/10/2021 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 6/10/2021 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 6/10/2021 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 7/1/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 9/3/2021 Corrections Issued MARK JOHNSON
Green Building Rough 9/3/2021 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 9/23/2021 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 9/23/2021 Partial Approval MARK JOHNSON
Green Building Rough 9/23/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 9/23/2021 Partial Approval MARK JOHNSON
Drywall Nailing 10/8/2021 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 10/8/2021 Not Ready for Inspection MARK JOHNSON
Green Building Rough 10/8/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 10/8/2021 Approved MARK JOHNSON
PLUMBING-Rough 10/8/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 10/22/2021 Corrections Issued MARK JOHNSON
ELECTRICAL-Rough 10/22/2021 Approved MARK JOHNSON
Green Building Rough 10/22/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 11/10/2021 Approved MARK JOHNSON
Drywall Nailing 11/10/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 11/10/2021 Partial Approval MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 1/27/2022 SGSOV Not Ready MICHAEL TEMPLE
ELECTRICAL-Final 2/9/2022 Corrections Issued RAUL OLAGI
Final 2/9/2022 Corrections Issued RAUL OLAGI
Green Building Final 2/9/2022 Corrections Issued RAUL OLAGI
HVAC-Final 2/9/2022 Corrections Issued RAUL OLAGI
PLUMBING-Final 2/9/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/9/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 2/9/2022 Approved RAUL OLAGI
Final 3/7/2022 Corrections Issued MICHAEL TEMPLE
Green Building Final 3/7/2022 Approved MICHAEL TEMPLE
Final 3/18/2022 OK to Issue CofO RAUL OLAGI