3332 E THORPE AVE 90065

Certificate Information: 3332 E THORPE AVE 90065

Application / Permit
20016-20000-19177
Plan Check / Job No.
B20VN10270
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) REC. ROOM AND STORAGE INTO A N ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 9/24/2020
Issuing Office
Current Status
CofO Issued on 2/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2020 APPLICANT
Assigned to Plan Check Engineer 8/14/2020 SAMUEL GONZALEZ
Corrections Issued 8/14/2020 SAMUEL GONZALEZ
Plan Check Approved 9/15/2020 RICHARD GARCIA
Issued 9/24/2020 APPLICANT
CofO in Progress 1/26/2021 OSVALDO PARAMO
CofO in Progress 1/26/2021 OSVALDO PARAMO
CofO in Progress 1/26/2021 OSVALDO PARAMO
Permit Finaled 2/25/2021 DEROLD HAUFF
CofO Issued 2/25/2021 DEROLD HAUFF
Permit Finaled 2/25/2021 DEROLD HAUFF

Permit Application Clearance Information

Supp. Use District POD/CDO/TDO Cleared 8/21/2020 ADRINEH MELKONIAN
Address approval Cleared 8/25/2020 ELAINE LEI
Sewer availability Cleared 8/25/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 8/26/2020 ELAINE LEI

Contact Information

Contractor Smart Construction Consultants Inc; Lic. No.: 1040768-B 5805 WHITE OAK AVE STE 17781      ENCINO, CA 91416
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/7/2020 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 10/9/2020 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/29/2020 Partial Approval OSVALDO PARAMO
Green Building Rough 10/29/2020 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Partial Approval OSVALDO PARAMO
Green Building Rough 11/20/2020 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 12/1/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/1/2020 Partial Approval OSVALDO PARAMO
Wood Frame 12/1/2020 Approved OSVALDO PARAMO
Insulation 12/7/2020 Approved OSVALDO PARAMO
Drywall Nailing 12/10/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/16/2020 Approved OSVALDO PARAMO
Final 1/11/2021 Corrections Issued RUBEN SALAS
Green Building Final 1/11/2021 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 1/11/2021 SGSOV Not Ready RUBEN SALAS
Smoke Detectors 1/11/2021 Approved RUBEN SALAS
Final 1/20/2021 Partial Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/20/2021 SGSOV Not Ready OSVALDO PARAMO
Final 1/25/2021 OK to Issue CofO OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/25/2021 SGSOV Approved OSVALDO PARAMO