9018 W 24TH ST 90034
Certificate Information: 9018 W 24TH ST 90034
- Application / Permit
- 20016-20000-19145
- Plan Check / Job No.
- B20VN10258
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) KITCHEN AND REMOVE WALLS AT KITCHEN AND LIVING ROOM. WORK PER ENGINEER.
- Permit Issued
- Issued on 10/20/2020
- Issuing Office
- Current Status
- Permit Finaled on 6/28/2021
Permit Application Status History
| Submitted | 8/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2020 | ROSENDO MEDINA |
| Corrections Issued | 8/22/2020 | ROSENDO MEDINA |
| Plan Check Approved | 10/8/2020 | ROSENDO MEDINA |
| Issued | 10/20/2020 | APPLICANT |
| Permit Finaled | 6/28/2021 | EVAN COOPER |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/17/2020 | KIRK LINKLATER |
Contact Information
| Contractor | Pro Star Builders Inc; Lic. No.: 1053661-B | 17412 VENTURA BLVD SUITE 151 ENCINO, CA 91316 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/2/2020 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 11/30/2020 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 12/3/2020 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 12/3/2020 | Approved | EVAN COOPER |
| HVAC-Rough | 12/3/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 12/3/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 12/9/2020 | Approved | EVAN COOPER |
| Drywall Nailing | 12/23/2020 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 4/23/2021 | Approved | EVAN COOPER |
| Final | 4/23/2021 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 4/23/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 4/23/2021 | Approved | EVAN COOPER |
| Smoke Detectors | 4/23/2021 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 5/3/2021 | Approved | EVAN COOPER |
| Final | 5/3/2021 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 5/3/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 5/3/2021 | Approved | EVAN COOPER |
| Smoke Detectors | 5/3/2021 | Approved | EVAN COOPER |
| Final | 6/28/2021 | Permit Finaled | EVAN COOPER |