5530 N WOODMAN AVE 91401

Certificate Information: 5530 N WOODMAN AVE 91401

Application / Permit
20016-20000-19084
Plan Check / Job No.
B20VN10233
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) 5'-0" x 17'-4" (150 SQ. FT.) PORCH OF (E) SINGLE FAMILY DWELLING INTO LIVING SPACE TO EXTEND THE (E) LIVING ROOM.
Permit Issued
Issued on 4/7/2021
Issuing Office
Current Status
CofO Issued on 4/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 ALFREDO JARA
Corrections Issued 9/14/2020 ALFREDO JARA
Applicant returned to address corrections 2/3/2021 SARKIS HARABEDIAN
Plan Check Approved 3/3/2021 SARKIS HARABEDIAN
Building Plans Picked Up 3/16/2021 APPLICANT
Issued 4/7/2021 APPLICANT
CofO in Progress 5/19/2022 RICHARD DOCKUS
Permit Finaled 4/17/2023 DANIEL ORRANTE
CofO Issued 4/17/2023 DANIEL ORRANTE
Permit Finaled 4/17/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/5/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 1/5/2021 JEANIE LAM

Contact Information

Contractor Lifetime Home Builders Inc; Lic. No.: 1050605-B 1545 NORTH VERDUGO RD STE 232      GLENDALE, CA 91208
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/14/2021 Corrections Issued MATTHEW NELSON
Deputy Drilled-In Anchors 4/15/2021 Approved MICHAEL TEMPLE
Footing/Foundation/Slab 4/15/2021 Corrections Issued MICHAEL TEMPLE
BUILDING-Rough-Frame 4/28/2021 Partial Approval JENNIFER RABUCHIN
Insulation 4/28/2021 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/12/2021 Not Ready for Inspection MICHAEL TEMPLE
ELECTRICAL-Rough 5/12/2021 Not Ready for Inspection MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Partial Approval MICHAEL TEMPLE
Wood Frame 5/12/2021 Not Ready for Inspection MICHAEL TEMPLE
ELECTRICAL-Rough 5/14/2021 Approved MICHEL ABAJAN
Wood Frame 5/14/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/17/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/17/2021 Approved JENNIFER RABUCHIN
Insulation 5/17/2021 Approved JENNIFER RABUCHIN
Drywall Nailing 5/25/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 5/25/2021 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 5/6/2022 Corrections Issued RICHARD DOCKUS
Final 5/6/2022 Not Ready for Inspection RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 5/6/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 5/6/2022 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 5/18/2022 Approved RICHARD DOCKUS
Final 5/18/2022 OK to Issue CofO RICHARD DOCKUS
Smoke Detectors 5/18/2022 Approved RICHARD DOCKUS