10541-10541 1/2 N LEV AVE 91345

Certificate Information: 10541-10541 1/2 N LEV AVE 91345

Application / Permit
20016-20000-19013
Plan Check / Job No.
B20VN10197
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). WORK DONE PER WFPP.
Permit Issued
Issued on 10/19/2020
Issuing Office
Current Status
CofO Issued on 4/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2020 APPLICANT
Assigned to Plan Check Engineer 8/14/2020 ROSENDO MEDINA
Corrections Issued 8/15/2020 ROSENDO MEDINA
Applicant returned to address corrections 8/31/2020 ROSENDO MEDINA
No Progress 9/1/2020 ROSENDO MEDINA
Applicant returned to address corrections 9/18/2020 ROSENDO MEDINA
Applicant returned to address corrections 10/14/2020 SARKIS HARABEDIAN
Plan Check Approved 10/16/2020 SARKIS HARABEDIAN
Issued 10/19/2020 APPLICANT
CofO in Progress 2/18/2021 MICHAEL TEMPLE
CofO Issued 4/10/2021 MICHAEL SMITH
Permit Finaled 4/10/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/1/2020 GUILLERMO PETRA
Sewer availability Cleared 10/1/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 10/15/2020 GUILLERMO PETRA

Contact Information

No Data Available.

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/13/2020 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 11/18/2020 Approved JENNIFER RABUCHIN
Sewer 11/18/2020 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/8/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 12/8/2020 Approved JENNIFER RABUCHIN
Green Building Rough 12/8/2020 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 12/8/2020 Approved JENNIFER RABUCHIN
Insulation 12/8/2020 Partial Approval JENNIFER RABUCHIN
METHANE-Rough 12/8/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 12/8/2020 Approved JENNIFER RABUCHIN
Insulation 12/10/2020 Approved JOHN HAYES
Interior/Exterior Lathing 12/10/2020 Partial Approval JOHN HAYES
Drywall Nailing 12/15/2020 Approved MISAEL ESPARZA
Shower Pan 12/15/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 1/6/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/17/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/17/2021 Approved JENNIFER RABUCHIN
Final 2/17/2021 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 2/17/2021 Approved JENNIFER RABUCHIN
Green Building Rough 2/17/2021 Approved JENNIFER RABUCHIN
HVAC-Final 2/17/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/17/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/17/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 2/17/2021 Approved JENNIFER RABUCHIN