4116 S CRENSHAW BLVD 90008
Certificate Information: 4116 S CRENSHAW BLVD 90008
- Application / Permit
- 20016-20000-18937
- Plan Check / Job No.
- B20VN10148
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE OF USE FROM (E) RETAIL TO (N) RESTAURANT. NEW COUNTERS, AND REMOVE NON BEARING PARTITIONS.
- Permit Issued
- Issued on 11/10/2020
- Issuing Office
- Current Status
- CofO Issued on 3/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 8/9/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 10/30/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 11/10/2020 | JEROME MAGAT PALMA |
| Issued | 11/10/2020 | APPLICANT |
| CofO in Progress | 2/22/2022 | RUSSELL BONVOULOIR |
| CofO Issued | 3/2/2022 | TED RIES |
| Permit Finaled | 3/2/2022 | TED RIES |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2020 | WALLIE JONG |
| Sewer availability | Cleared | 9/8/2020 | WALLIE JONG |
| Historic Resource Verification | Cleared | 9/9/2020 | MICAELA TORRES-GIL |
| Specific Plan | Cleared | 9/30/2020 | KYLE WINSTON |
| Redevelopment Project Area | Cleared | 10/9/2020 | DAVID URITA |
| Food Service Establishment | Cleared | 10/20/2020 | KENNETH BROWNE |
| Food establishment approval | Cleared | 11/4/2020 | LACDHS APPROVED |
| Specific Plan | Cleared | 11/10/2020 | KYLE WINSTON |
Contact Information
| Contractor | Urquia Marvin; Lic. No.: 1064984-B | 11146 VAN BUREN AVE LOS ANGELES, CA 90044 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/16/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 12/24/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Final | 6/9/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Smoke Detectors | 6/9/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 6/9/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Final | 9/21/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Smoke Detectors | 9/21/2021 | Approved | LEOPOLDO MENDOZA |
| Wood Frame | 9/21/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 11/17/2021 | Conditional Approval | RUSSELL BONVOULOIR |