12607 W WOODBINE ST 90066

Certificate Information: 12607 W WOODBINE ST 90066

Application / Permit
20016-20000-18858
Plan Check / Job No.
B20VN10122
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED INT/EXT REMODEL TO EX 2-STORY SFD: @ 1ST FLR - REMODEL TWO BATHRMS, ENLARGE EX DOOR IN REAR LIVING RM PER PLAN. RELOCATE DOORS TO BEDRMS. @ 2ND FLR - ENLARGE EX BATHRM & CONVERT EX CLOSET INTO BATHRM. REMOVE NONSTRUCT WALL BETWEEN TWO BEDRMS TO CREATE ONE BEDRM. ALL PER ENGR DESIGN.
Permit Issued
Issued on 10/16/2020
Issuing Office
Current Status
Permit Finaled on 8/13/2021

Permit Application Status History

Submitted 8/11/2020 APPLICANT
Assigned to Plan Check Engineer 8/18/2020 HAYATO TSUCHIYA
Corrections Issued 8/19/2020 HAYATO TSUCHIYA
Plan Check Approved 9/11/2020 HAYATO TSUCHIYA
Issued 10/16/2020 APPLICANT
Permit Finaled 8/13/2021 ENRIQUE MIRELES

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/28/2020 BARTON HOLMES

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Bela Development; Lic. No.: 1038287-B 1101 OCEAN FRONT WALK #22      LOS ANGELES, CA 90291

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/19/2020 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 10/19/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 10/19/2020 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 10/22/2020 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 10/22/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 10/22/2020 Approved ENRIQUE MIRELES
Drywall Nailing 10/29/2020 Partial Approval DAVID HEINE
Shower Pan 10/29/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 11/9/2020 Corrections Issued JUAN VALENZUELA
Interior/Exterior Lathing 11/9/2020 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 11/16/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/16/2020 Not Ready for Inspection ENRIQUE MIRELES
Final 3/15/2021 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 3/15/2021 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 3/15/2021 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/18/2021 Corrections Issued ANTHONY MCDOWALL
Insulation 3/18/2021 Partial Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 3/24/2021 Approved ENRIQUE MIRELES
Deputy Wood Construction 3/31/2021 Approved ENRIQUE MIRELES
Drywall Nailing 3/31/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/6/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 5/6/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/12/2021 Approved ENRIQUE MIRELES
Drywall Nailing 5/21/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/21/2021 Approved ENRIQUE MIRELES
Final 8/13/2021 Permit Finaled ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/13/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 8/13/2021 Approved ENRIQUE MIRELES