22725 W CAVALIER ST 91364
Certificate Information: 22725 W CAVALIER ST 91364
- Application / Permit
- 20016-20000-18716
- Plan Check / Job No.
- B20VN10069
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 20' x 20' DET. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- CofO Issued on 12/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2020 | TSE MING HUANG |
| Corrections Issued | 8/9/2020 | TSE MING HUANG |
| Plan Check Approved | 1/5/2022 | ANGELICA MARTINEZ |
| Issued | 3/22/2022 | APPLICANT |
| CofO in Progress | 11/17/2022 | PETER FOLLING |
| Permit Finaled | 12/9/2022 | MICHAEL SMITH |
| CofO Issued | 12/9/2022 | MICHAEL SMITH |
| Permit Finaled | 12/9/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/22/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 10/16/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 10/16/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/16/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2020 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 12/18/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/18/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tabar,, Mehrdad; Lic. No.: C37433 | 14252 CULVER DR A349 IRVINE, CA 92604 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/19/2022 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 5/6/2022 | Corrections Issued | PETER FOLLING |
| Deputy Drilled-In Anchors | 6/1/2022 | Conditional Approval | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 6/9/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 6/23/2022 | Approved | PETER FOLLING |
| HVAC-Rough | 6/29/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 6/29/2022 | Partial Approval | PETER FOLLING |
| PLUMBING-Rough | 6/29/2022 | Approved | PETER FOLLING |
| Insulation | 7/7/2022 | Approved | PETER FOLLING |
| Sewer | 7/7/2022 | Approved | PETER FOLLING |
| Drywall Nailing | 7/13/2022 | Not Ready for Inspection | PETER FOLLING |
| Green Building Rough | 7/13/2022 | Approved | PETER FOLLING |
| Drywall Nailing | 7/26/2022 | Not Ready for Inspection | MORRIS JACKSON |
| Drywall Nailing | 8/1/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 8/22/2022 | Corrections Issued | JESUS PINEDA |
| Shower Pan | 8/24/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 9/2/2022 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 9/30/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 10/17/2022 | Approved | HENRY KIM |
| ELECTRICAL-Final | 10/17/2022 | Corrections Issued | HENRY KIM |
| Final | 10/17/2022 | Corrections Issued | HENRY KIM |
| Green Building Final | 10/17/2022 | Corrections Issued | HENRY KIM |
| HVAC-Final | 10/17/2022 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 10/17/2022 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 10/17/2022 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 10/17/2022 | Corrections Issued | HENRY KIM |
| Final | 11/16/2022 | OK to Issue CofO | PETER FOLLING |
| Green Building Final | 11/16/2022 | Approved | PETER FOLLING |
| Smoke Detectors | 11/16/2022 | Approved | PETER FOLLING |