22739 W ERWIN ST 91367
Certificate Information: 22739 W ERWIN ST 91367
- Application / Permit
- 20016-20000-18460
- Plan Check / Job No.
- B20VN09969
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) GARAGE AND A PORTION OF THE (E) WORKSHOP INTO A (N) ACCESSORY DWELLING UNIT (20'-0"x43'-0") per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/4/2021
- Issuing Office
- Current Status
- CofO Issued on 4/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 8/15/2020 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 8/18/2020 | APPLICANT |
| Plan Check Approved | 3/3/2021 | MOHAMMAD ESMAILI |
| Issued | 3/4/2021 | APPLICANT |
| CofO in Progress | 4/12/2023 | TROY SANDERS |
| Permit Finaled | 4/14/2023 | JOHN JANSON |
| CofO Issued | 4/14/2023 | JOHN JANSON |
| Permit Finaled | 4/14/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 9/9/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 9/9/2020 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 9/10/2020 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2020 | GUILLERMO PETRA |
| Certificate of Compliance | Cleared | 11/30/2020 | HERMINIGILDO AGUSTIN |
| GPI Written Notices | Cleared | 3/3/2021 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/20/2022 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 5/20/2022 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 7/8/2022 | Approved | TROY SANDERS |
| Special/Order Compliance | 7/8/2022 | Corrections Issued | TROY SANDERS |
| ELECTRICAL-Rough | 8/30/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 8/30/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 9/7/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 10/5/2022 | Approved | TROY SANDERS |
| Green Building Rough | 10/5/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/5/2022 | Partial Approval | TROY SANDERS |
| Insulation | 10/12/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 10/20/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/25/2022 | Partial Approval | TROY SANDERS |
| Shower Pan | 10/25/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Not Ready | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Not Ready | TROY SANDERS |
| Final | 4/11/2023 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 4/11/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/11/2023 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 4/11/2023 | Approved | TROY SANDERS |