9582 N SANDUSKY AVE 91331

Certificate Information: 9582 N SANDUSKY AVE 91331

Application / Permit
20016-20000-18418
Plan Check / Job No.
B20VN09943
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20 DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER ENGINEER.
Permit Issued
Issued on 7/22/2021
Issuing Office
Current Status
CofO Issued on 10/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2020 APPLICANT
Assigned to Plan Check Engineer 8/10/2020 ROSENDO MEDINA
Corrections Issued 8/11/2020 ROSENDO MEDINA
Applicant returned to address corrections 3/21/2021 RAPHAEL ROSAS
Plan Check Approved 7/14/2021 ROSENDO MEDINA
Issued 7/22/2021 APPLICANT
Building Plans Picked Up 7/26/2021 APPLICANT
CofO in Progress 10/14/2022 ALAN MORELOS
CofO Issued 10/29/2022 MICHAEL SMITH
Permit Finaled 10/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/3/2020 ADRIAN CASTRO
Sewer availability Cleared 9/3/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/8/2020 ADRIAN CASTRO
Construction near power lines Cleared 7/7/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/27/2021 Conditional Approval GREGG CUMMINGS
Footing/Foundation/Slab 7/29/2021 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 8/2/2021 Approved JOHN HAYES
Pre-Inspection 8/24/2021 Approved GREGG CUMMINGS
ELECTRICAL-Rough 11/12/2021 Approved GREGG CUMMINGS
Interior/Exterior Lathing 11/12/2021 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 11/12/2021 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 11/30/2021 Conditional Approval WILLIAM WREN
Insulation 11/30/2021 Approved WILLIAM WREN
BUILDING-Rough-Frame 12/6/2021 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 12/9/2021 Approved CHRISTOPHER DELLEFIELD
Insulation 12/9/2021 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 12/20/2021 Approved GREGG CUMMINGS
Green Building Rough 12/20/2021 Approved GREGG CUMMINGS
Insulation 12/20/2021 Approved GREGG CUMMINGS
Drywall Nailing 2/10/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 2/10/2022 Corrections Issued WILLIAM WREN
Interior/Exterior Lathing 4/1/2022 Partial Approval MISAEL ESPARZA
Final 8/31/2022 Corrections Issued DEANDRE HOFFMAN
Green Building Final 8/31/2022 Corrections Issued DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 8/31/2022 Corrections Issued DEANDRE HOFFMAN
Final 9/23/2022 Corrections Issued GREGG CUMMINGS
Final 10/5/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 10/5/2022 Approved GREGG CUMMINGS
Smoke Detectors 10/5/2022 Approved GREGG CUMMINGS
ELECTRICAL-Final 10/13/2022 Approved ALAN MORELOS
Final 10/13/2022 OK to Issue CofO ALAN MORELOS
HVAC-Final 10/13/2022 Approved ALAN MORELOS
PLUMBING-Final 10/13/2022 Approved ALAN MORELOS