6229 N CARTWRIGHT AVE 91606

Certificate Information: 6229 N CARTWRIGHT AVE 91606

Application / Permit
20016-20000-18343
Plan Check / Job No.
B20VN09917
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-1" X 20'-4" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 9/10/2020
Issuing Office
Current Status
CofO Issued on 5/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 HAYATO TSUCHIYA
Corrections Issued 8/10/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 8/24/2020 JENNIFER LEE
Plan Check Approved 9/8/2020 JENNIFER LEE
Issued 9/10/2020 APPLICANT
CofO in Progress 3/25/2021 DANIEL DREW
Permit Finaled 5/5/2021 MICHAEL SMITH
CofO Issued 5/5/2021 MICHAEL SMITH
Permit Finaled 5/5/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/14/2020 GABRIEL ROBLES
Sewer availability Cleared 8/14/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/17/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/6/2020 Approved DANIEL DREW
Underground Mechanical 10/6/2020 Approved DANIEL DREW
Excavation/Setback/Form/Re-Bar 10/13/2020 Conditional Approval DANIEL DREW
BUILDING-Rough-Frame 11/5/2020 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Rough 11/5/2020 Approved DANIEL DREW
Green Building Rough 11/5/2020 Not Ready for Inspection DANIEL DREW
Insulation 11/5/2020 Not Ready for Inspection DANIEL DREW
PLUMBING-Rough 11/5/2020 Approved DANIEL DREW
Drywall Nailing 11/10/2020 Approved DANIEL DREW
Green Building Rough 11/10/2020 Approved DANIEL DREW
Insulation 11/10/2020 Approved DANIEL DREW
Underground Mechanical 11/10/2020 Approved DANIEL DREW
Shower Pan 11/17/2020 Approved DANIEL DREW
Interior/Exterior Lathing 12/17/2020 Approved DANIEL DREW
ELECTRICAL-Final 2/19/2021 Corrections Issued DANIEL DREW
Service/Power Release 2/19/2021 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Final 3/3/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 3/17/2021 Approved DANIEL DREW
Final 3/17/2021 Not Ready for Inspection DANIEL DREW
Green Building Final 3/17/2021 Not Ready for Inspection DANIEL DREW
SGSOV-Seismic Gas S/O Valve 3/17/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 3/17/2021 Approved DANIEL DREW
ELECTRICAL-Final 3/25/2021 Approved DANIEL DREW
Final 3/25/2021 OK to Issue CofO DANIEL DREW
Green Building Final 3/25/2021 Approved DANIEL DREW
HVAC-Final 3/25/2021 Approved DANIEL DREW
PLUMBING-Final 3/25/2021 Approved DANIEL DREW