18022 W PENROSE ST 91352

Certificate Information: 18022 W PENROSE ST 91352

Application / Permit
20016-20000-18135
Plan Check / Job No.
B20VN09817
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 10/9/2020
Issuing Office
Current Status
CofO Issued on 4/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2020 APPLICANT
Assigned to Plan Check Engineer 7/31/2020 ROSENDO MEDINA
Corrections Issued 8/3/2020 ROSENDO MEDINA
Applicant returned to address corrections 9/10/2020 ROSENDO MEDINA
Applicant returned to address corrections 9/16/2020 ROSENDO MEDINA
Applicant returned to address corrections 9/25/2020 ROSENDO MEDINA
Plan Check Approved 10/8/2020 ROSENDO MEDINA
Issued 10/9/2020 APPLICANT
CofO in Progress 3/21/2023 DAVID ANDERSON
CofO Issued 4/5/2023 DANIEL ORRANTE
Permit Finaled 4/5/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/5/2020 GABRIEL ROBLES
Sewer availability Cleared 8/5/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/3/2020 GABRIEL ROBLES
Specific Plan Cleared 9/28/2020 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 10/1/2020 BARTON HOLMES

Contact Information

Contractor Whitehouse Builders; Lic. No.: 956410-B P O BOX 552      CASTAIC, CA 91310

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/28/2021 Conditional Approval BEAU COLLINS
Underground Mechanical 1/28/2021 Corrections Issued BEAU COLLINS
BUILDING-Rough-Frame 6/15/2022 Approved DAVID ANDERSON
ELECTRICAL-Rough 6/15/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Approved DAVID ANDERSON
Green Building Rough 6/15/2022 Approved DAVID ANDERSON
HVAC-Rough 6/15/2022 Approved DAVID ANDERSON
PLUMBING-Rough 6/15/2022 Approved DAVID ANDERSON
Insulation 6/22/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/22/2022 Approved DAVID ANDERSON
Drywall Nailing 7/27/2022 Approved DAVID ANDERSON
ELECTRICAL-Final 3/13/2023 Not Ready for Inspection DAVID ANDERSON
Final 3/13/2023 Corrections Issued DAVID ANDERSON
Green Building Final 3/13/2023 Not Ready for Inspection DAVID ANDERSON
HVAC-Final 3/13/2023 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Final 3/13/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/13/2023 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 3/13/2023 Approved DAVID ANDERSON
ELECTRICAL-Final 3/20/2023 Approved DAVID ANDERSON
Final 3/20/2023 OK to Issue CofO DAVID ANDERSON
Green Building Final 3/20/2023 Approved DAVID ANDERSON
HVAC-Final 3/20/2023 Approved DAVID ANDERSON
PLUMBING-Final 3/20/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/20/2023 SGSOV Approved DAVID ANDERSON