755 N LAS PALMAS AVE 90038

Certificate Information: 755 N LAS PALMAS AVE 90038

Application / Permit
20016-20000-17995
Plan Check / Job No.
B20VN09751
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE/ RECREATION ROOM TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 12/3/2020
Issuing Office
Current Status
CofO Issued on 4/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2020 APPLICANT
Assigned to Plan Check Engineer 7/29/2020 ROSENDO MEDINA
Corrections Issued 7/30/2020 ROSENDO MEDINA
Plan Check Approved 12/3/2020 ROSENDO MEDINA
Issued 12/3/2020 APPLICANT
CofO in Progress 3/29/2021 BRIAN SULLIVAN
Permit Finaled 4/14/2021 DEROLD HAUFF
CofO Issued 4/14/2021 DEROLD HAUFF
Permit Finaled 4/14/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/13/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/13/2020 WALLIE JONG
Sewer availability Cleared 8/13/2020 WALLIE JONG
Construction near power lines Cleared 12/3/2020 OSCAR CASTRO

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Karma Remodel & Development Inc; Lic. No.: 875130-B 21610 VENTURA BLVD      WOODLAND HILLS, CA 91364

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/24/2020 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 12/24/2020 Conditional Approval JOSEPH MCGARRY
Gas Test 12/24/2020 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 12/24/2020 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 1/14/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 1/14/2021 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 1/14/2021 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 1/14/2021 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Rough 1/14/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 1/20/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 1/20/2021 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 Approved BRIAN SULLIVAN
Green Building Rough 1/20/2021 Approved BRIAN SULLIVAN
HVAC-Rough 1/20/2021 Approved BRIAN SULLIVAN
Insulation 2/1/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 2/1/2021 Not Ready for Inspection BRIAN SULLIVAN
Drywall Nailing 2/12/2021 Approved SCOTT FINNILA
Interior/Exterior Lathing 2/12/2021 Partial Approval SCOTT FINNILA
Sewer 2/12/2021 Corrections Issued SCOTT FINNILA
Sewer 2/19/2021 Approved BRIAN SULLIVAN
Final 3/11/2021 No Access for Inspection BRIAN SULLIVAN
Green Building Final 3/11/2021 No Access for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 3/11/2021 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 3/11/2021 No Access for Inspection BRIAN SULLIVAN
Final 3/17/2021 Corrections Issued BRIAN SULLIVAN
Green Building Final 3/17/2021 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 3/17/2021 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 3/17/2021 Approved BRIAN SULLIVAN
Final 3/23/2021 Not Ready for Inspection BRIAN SULLIVAN
Green Building Final 3/23/2021 Approved BRIAN SULLIVAN
Final 3/26/2021 OK to Issue CofO BRIAN SULLIVAN