3738 N BERRY DR 91604

Certificate Information: 3738 N BERRY DR 91604

Application / Permit
20016-20000-17985
Plan Check / Job No.
B20VN09747
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 25' 4" X 18' 7" DETACHED GARAGE/STORAGE TO ADU W/ ATTACHED PATIO COVER. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 12/4/2020
Issuing Office
Current Status
CofO Issued on 11/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2020 APPLICANT
Assigned to Plan Check Engineer 8/5/2020 GURUNATH NESARAJAH
Corrections Issued 8/5/2020 GURUNATH NESARAJAH
Building Plans Picked Up 8/11/2020 APPLICANT
Plan Check Approved 11/4/2020 GURUNATH NESARAJAH
Issued 12/4/2020 APPLICANT
CofO in Progress 9/13/2021 ARAM AVEDISIAN
CofO Issued 11/30/2021 MICHAEL SMITH
Permit Finaled 11/30/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/17/2020 GABRIEL ROBLES
Sewer availability Cleared 8/17/2020 GABRIEL ROBLES
Miscellaneous Cleared 8/19/2020 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 8/20/2020 GABRIEL ROBLES
Specific Plan Cleared 10/8/2020 TRACY WILLIAMS
Grading Pre-Inspection Cleared 10/23/2020 GURUNATH NESARAJAH

Contact Information

Contractor A G Builders & Development Corp; Lic. No.: 959503-B 7657 WINNETKA AVE #341      WINNETKA, CA 91306
Engineer Sayah,, Daniel Hoshyar; Lic. No.: S6000 15233 VENTURA BLVD 1130      SHERMAN OAKS, CA 91403

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/12/2021 Approved JOHN HAYES
Pre-Inspection 3/16/2021 Partial Inspection ARAM AVEDISIAN
Shower Pan 3/23/2021 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 4/8/2021 Approved ARAM AVEDISIAN
HVAC-Rough 4/8/2021 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 4/8/2021 Approved ARAM AVEDISIAN
Wood Frame 4/8/2021 Approved ARAM AVEDISIAN
Insulation 4/19/2021 Approved ARAM AVEDISIAN
Drywall Nailing 4/28/2021 Partial Approval KRISTEN CAUSEY
Pre-Inspection 4/28/2021 Partial Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 8/26/2021 Approved ARAM AVEDISIAN
Final 8/26/2021 Corrections Issued ARAM AVEDISIAN
Green Building Final 8/26/2021 Approved ARAM AVEDISIAN
Green Building Rough 8/26/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/26/2021 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 8/26/2021 Approved ARAM AVEDISIAN
Final 8/31/2021 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/31/2021 SGSOV Approved ARAM AVEDISIAN
Final 9/8/2021 Not Ready for Inspection ARAM AVEDISIAN
Final 9/10/2021 Corrections Issued JOHN HAYES
Final 9/13/2021 OK to Issue CofO ARAM AVEDISIAN