5453 N BECK AVE 91601

Certificate Information: 5453 N BECK AVE 91601

Application / Permit
20016-20000-17984
Plan Check / Job No.
B20VN09746
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 9/16/2020
Issuing Office
Current Status
CofO Issued on 7/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2020 APPLICANT
Assigned to Plan Check Engineer 7/29/2020 ROSENDO MEDINA
Corrections Issued 7/30/2020 ROSENDO MEDINA
Plan Check Approved 9/1/2020 ROSENDO MEDINA
Issued 9/16/2020 APPLICANT
CofO in Progress 5/12/2022 THOMAS FINNILA
CofO in Progress 5/12/2022 THOMAS FINNILA
Permit Finaled 7/11/2022 MICHAEL SMITH
CofO Issued 7/11/2022 MICHAEL SMITH
Permit Finaled 7/11/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/4/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/4/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/5/2020 JOHN TRIANTAFYLLOS
Miscellaneous Cleared 8/5/2020 MIGUEL GAMBOA
Miscellaneous Cleared 8/5/2020 MIGUEL GAMBOA
Miscellaneous Cleared 8/5/2020 MIGUEL GAMBOA

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/28/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 9/28/2020 Not Ready for Inspection THOMAS FINNILA
Sewer 9/28/2020 Not Ready for Inspection THOMAS FINNILA
Sewer 10/6/2020 Approved THOMAS FINNILA
Footing/Foundation/Slab 10/14/2020 Partial Approval THOMAS FINNILA
Deputy Drilled-In Anchors 10/22/2020 Approved THOMAS FINNILA
Footing/Foundation/Slab 10/22/2020 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 10/28/2020 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 11/6/2020 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/10/2020 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 1/4/2021 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 1/4/2021 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 1/4/2021 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 1/11/2021 Partial Inspection THOMAS FINNILA
ELECTRICAL-Rough 1/20/2021 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 1/20/2021 Partial Inspection THOMAS FINNILA
Gas Test 2/3/2021 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 2/9/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 2/9/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 2/9/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 2/9/2021 Not Ready for Inspection JOHN HAYES
MERV13>=Rough 2/9/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 2/9/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 2/12/2021 Partial Approval THOMAS FINNILA
MERV13>=Rough 2/12/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 2/12/2021 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 2/18/2021 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 2/23/2021 Approved THOMAS FINNILA
Green Building Rough 2/23/2021 Approved THOMAS FINNILA
Insulation 2/23/2021 Approved THOMAS FINNILA
MERV13>=Rough 2/23/2021 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/3/2021 Approved THOMAS FINNILA
Drywall Nailing 3/12/2021 Approved THOMAS FINNILA
Shower Pan 4/19/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 4/26/2021 Approved THOMAS FINNILA
Final 5/18/2021 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 5/18/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 5/18/2021 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 5/18/2021 SGSOV Approved THOMAS FINNILA
PLUMBING-Final 6/10/2021 Approved THOMAS FINNILA
Final 6/11/2021 Not Ready for Inspection THOMAS FINNILA
Green Building Final 6/11/2021 Not Ready for Inspection THOMAS FINNILA
MERV13>=Final 6/11/2021 Approved THOMAS FINNILA
Smoke Detectors 6/11/2021 Approved THOMAS FINNILA
Final 6/30/2021 OK to Issue CofO THOMAS FINNILA
Green Building Final 6/30/2021 Approved THOMAS FINNILA