6915-6917 N KATHERINE AVE 91405

Certificate Information: 6915-6917 N KATHERINE AVE 91405

Application / Permit
20016-20000-17861
Plan Check / Job No.
B20VN09702
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20' X 22' ATTACHED GARAGE TO ADU. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 9/18/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2020 APPLICANT
Assigned to Plan Check Engineer 8/10/2020 GURUNATH NESARAJAH
Corrections Issued 8/11/2020 GURUNATH NESARAJAH
Plan Check Approved 8/31/2020 GURUNATH NESARAJAH
Issued 9/18/2020 APPLICANT
CofO in Progress 3/12/2021 MICHEL ABAJAN
CofO Issued 4/10/2021 MICHAEL SMITH
Permit Finaled 4/10/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/13/2020 ADRIAN CASTRO
Sewer availability Cleared 8/13/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/26/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/12/2020 Approved MISAEL ESPARZA
ELECTRICAL-Rough 11/12/2020 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 11/12/2020 Partial Inspection WILLIAM KUEHN
Footing/Foundation/Slab 11/12/2020 Approved WILLIAM KUEHN
PLUMBING-Rough 11/12/2020 Approved WILLIAM KUEHN
Wood Frame 11/12/2020 Approved WILLIAM KUEHN
Insulation 11/19/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/19/2020 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 11/25/2020 Approved WILLIAM KUEHN
Shower Pan 11/25/2020 Corrections Issued WILLIAM KUEHN
Shower Pan 12/2/2020 Corrections Issued JENNIFER RABUCHIN
Shower Pan 12/4/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 1/27/2021 Not Ready for Inspection JOHN HAYES
Final 1/27/2021 Corrections Issued JOHN HAYES
Green Building Final 1/27/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 1/27/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 1/27/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 2/5/2021 Approved DAVID SCANTLIN
Final 2/5/2021 Corrections Issued DAVID SCANTLIN
Green Building Final 2/5/2021 Approved DAVID SCANTLIN
Green Building Rough 2/5/2021 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 2/5/2021 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 2/5/2021 Approved DAVID SCANTLIN
Final 2/23/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 2/23/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/23/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/23/2021 SGSOV Approved JENNIFER RABUCHIN
Final 3/12/2021 OK to Issue CofO MICHEL ABAJAN