6504 N GAVIOTA AVE 91406

Certificate Information: 6504 N GAVIOTA AVE 91406

Application / Permit
20016-20000-17859
Plan Check / Job No.
B20VN09701
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF (E) GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d), ALL WORKS PER WFPP
Permit Issued
Issued on 1/14/2021
Issuing Office
Current Status
CofO Issued on 6/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2020 APPLICANT
Assigned to Plan Check Engineer 8/13/2020 MOHAMMAD ESMAILI
Corrections Issued 8/18/2020 MOHAMMAD ESMAILI
Quality Review Completed 9/2/2020 OMID HEDAYAT
Building Plans Picked Up 9/4/2020 APPLICANT
Plan Check Approved 1/14/2021 MOHAMMAD ESMAILI
Issued 1/14/2021 APPLICANT
CofO in Progress 1/31/2022 RAUL OLAGI
Permit Finaled 6/20/2022 MICHAEL SMITH
CofO Issued 6/20/2022 MICHAEL SMITH
Permit Finaled 6/20/2022 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 10/20/2020 SARAH YOUSSEF
Address approval Cleared 10/29/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/29/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 10/29/2020 ADRIAN CASTRO
Sewer availability Cleared 10/29/2020 ADRIAN CASTRO
ZI Cleared 11/5/2020 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/16/2021 Approved ARTHUR SARGSYAN
Underground Mechanical 4/16/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 4/26/2021 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 5/25/2021 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 5/25/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Rough 5/25/2021 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 5/25/2021 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 6/22/2021 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 7/12/2021 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 7/12/2021 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 7/26/2021 Approved WILLIAM KUEHN
PLUMBING-Rough 7/26/2021 Approved WILLIAM KUEHN
Shower Pan 7/26/2021 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 7/28/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 7/28/2021 Partial Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 7/28/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/2/2021 Partial Inspection JACK KARGODORIAN
Green Building Rough 8/2/2021 Approved JACK KARGODORIAN
HVAC-Rough 8/2/2021 Approved JACK KARGODORIAN
Insulation 8/2/2021 Approved JACK KARGODORIAN
Wood Frame 8/4/2021 Approved JACK KARGODORIAN
Drywall Nailing 8/10/2021 Corrections Issued DEANDRE HOFFMAN
Drywall Nailing 8/12/2021 Approved JACK KARGODORIAN
Interior/Exterior Lathing 8/16/2021 Approved AMY COLIN
Interior/Exterior Lathing 9/8/2021 Approved AMY COLIN
BUILDING-Rough-Frame 11/9/2021 Approved RAUL OLAGI
Final 11/9/2021 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 11/9/2021 Approved RAUL OLAGI
Green Building Final 11/9/2021 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 11/9/2021 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 11/9/2021 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 12/13/2021 SGSOV Not Ready RAUL OLAGI
Final 1/18/2022 Corrections Issued RAUL OLAGI
Green Building Final 1/18/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 1/18/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 1/18/2022 Approved RAUL OLAGI
Final 1/31/2022 OK to Issue CofO RAUL OLAGI
Green Building Final 1/31/2022 Approved RAUL OLAGI