12950 W JUDD ST 91331
Certificate Information: 12950 W JUDD ST 91331
- Application / Permit
- 20016-20000-17826
- Plan Check / Job No.
- B20VN09679
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-4" X 19'-0" GARAGE TO ACCESSORY DWELLING UNIT (363 SQ FT).
- Permit Issued
- Issued on 2/1/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 8/3/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/31/2020 | JEROME MAGAT PALMA |
| Issued | 2/1/2021 | APPLICANT |
| CofO in Progress | 12/14/2021 | MICHEL ABAJAN |
| CofO Issued | 1/22/2022 | MICHAEL SMITH |
| Permit Finaled | 1/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 8/10/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 12/16/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/19/2021 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/13/2021 | Approved | MICHEL ABAJAN |
| Gas Test | 4/13/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/13/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/19/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/19/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2021 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 5/19/2021 | Approved | MICHEL ABAJAN |
| Insulation | 5/19/2021 | Partial Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/19/2021 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 5/19/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/19/2021 | Approved | MICHEL ABAJAN |
| Insulation | 5/27/2021 | Approved | MICHEL ABAJAN |
| Shower Pan | 5/27/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/9/2021 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 10/29/2021 | SGSOV Not Ready | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/2/2021 | Approved | MICHEL ABAJAN |
| Final | 11/2/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 11/2/2021 | Approved | MICHEL ABAJAN |
| HVAC-Final | 11/2/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/2/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/2/2021 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 11/2/2021 | Approved | MICHEL ABAJAN |
| Final | 12/14/2021 | OK to Issue CofO | MICHEL ABAJAN |