19320 W HART ST 91335

Certificate Information: 19320 W HART ST 91335

Application / Permit
20016-20000-17809
Plan Check / Job No.
B20VN09664
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (380 SQ FT).
Permit Issued
Issued on 10/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2020 APPLICANT
Assigned to Plan Check Engineer 7/29/2020 JEROME MAGAT PALMA
Corrections Issued 7/29/2020 JEROME MAGAT PALMA
Plan Check Approved 9/3/2020 SARKIS HARABEDIAN
Issued 10/5/2020 APPLICANT
CofO in Progress 5/13/2021 VINCENT HANLEY
Permit Finaled 5/13/2021 JOHN JANSON
CofO Issued 5/13/2021 JOHN JANSON
Permit Finaled 5/13/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/6/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/6/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/6/2020 JOHN TRIANTAFYLLOS
ZI Cleared 8/20/2020 TERRI OSBORNE

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/10/2020 Approved VINCENT HANLEY
Gas Test 11/10/2020 Partial Approval VINCENT HANLEY
PLUMBING-Rough 11/10/2020 Partial Approval VINCENT HANLEY
Sewer 11/10/2020 Approved VINCENT HANLEY
Underground Mechanical 11/10/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 11/20/2020 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 11/20/2020 Approved VINCENT HANLEY
Gas Test 11/20/2020 Partial Approval VINCENT HANLEY
Green Building Rough 11/20/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 11/20/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/30/2020 Approved VINCENT HANLEY
Green Building Rough 11/30/2020 Approved VINCENT HANLEY
HVAC-Rough 11/30/2020 Approved VINCENT HANLEY
Insulation 11/30/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/2/2020 Approved VINCENT HANLEY
Drywall Nailing 12/2/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Approved VINCENT HANLEY
Green Building Rough 12/2/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/17/2020 Approved VINCENT HANLEY
Shower Pan 12/24/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 1/27/2021 Corrections Issued VINCENT HANLEY
Final 1/27/2021 Not Ready for Inspection VINCENT HANLEY
Green Building Final 1/27/2021 Approved VINCENT HANLEY
HVAC-Final 1/27/2021 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 1/27/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 4/27/2021 Approved VINCENT HANLEY
Final 4/27/2021 Corrections Issued VINCENT HANLEY
HVAC-Final 4/27/2021 Corrections Issued VINCENT HANLEY
Final 5/13/2021 OK to Issue CofO VINCENT HANLEY