3226 1/2 W 27TH ST 90018
Certificate Information: 3226 1/2 W 27TH ST 90018
- Application / Permit
- 20016-20000-17663
- Plan Check / Job No.
- B20VN09606
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 21'-7" X 22'-0" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 9/30/2020
- Issuing Office
- Current Status
- CofO Issued on 2/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2020 | JENNIFER LEE |
| Corrections Issued | 7/29/2020 | JENNIFER LEE |
| Plan Check Approved | 9/29/2020 | JENNIFER LEE |
| Issued | 9/30/2020 | APPLICANT |
| CofO in Progress | 1/19/2021 | STUART CHAPMAN |
| Permit Finaled | 2/2/2021 | DEROLD HAUFF |
| CofO Issued | 2/2/2021 | DEROLD HAUFF |
| Permit Finaled | 2/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 8/3/2020 | LAUREN PADICK |
| Miscellaneous | Cleared | 8/3/2020 | LAUREN PADICK |
| Miscellaneous | Cleared | 8/3/2020 | LAUREN PADICK |
| Address approval | Cleared | 8/11/2020 | JEANIE LAM |
| Sewer availability | Cleared | 8/11/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2020 | JEANIE LAM |
| HPOZ | Cleared | 9/17/2020 | MAX LODER |
| ZI | Cleared | 9/17/2020 | MAX LODER |
| ZI | Cleared | 9/17/2020 | MAX LODER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/9/2020 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 10/9/2020 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 10/9/2020 | Partial Inspection | RUBEN SALAS |
| Underground Mechanical | 10/19/2020 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2020 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 10/22/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 10/22/2020 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/28/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 10/28/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 10/28/2020 | Approved | STUART CHAPMAN |
| HVAC-Rough | 10/28/2020 | Approved | STUART CHAPMAN |
| METHANE-Rough | 10/28/2020 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/2/2020 | Partial Approval | STUART CHAPMAN |
| Insulation | 11/4/2020 | Approved | STUART CHAPMAN |
| Drywall Nailing | 11/9/2020 | Approved | STUART CHAPMAN |
| Shower Pan | 11/9/2020 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/18/2020 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Final | 12/29/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 12/29/2020 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 12/29/2020 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Final | 12/29/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 12/29/2020 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2020 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 12/29/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 12/31/2020 | Approved | STUART CHAPMAN |
| Final | 12/31/2020 | Conditional Approval | STUART CHAPMAN |
| Green Building Final | 12/31/2020 | Approved | STUART CHAPMAN |
| HVAC-Final | 12/31/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 12/31/2020 | Approved | STUART CHAPMAN |