22326-22328 W GILMORE ST 91303

Certificate Information: 22326-22328 W GILMORE ST 91303

Application / Permit
20016-20000-17644
Plan Check / Job No.
B20VN09600
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT (365 SQ FT)
Permit Issued
Issued on 10/31/2020
Issuing Office
Current Status
CofO Issued on 9/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2020 APPLICANT
Assigned to Plan Check Engineer 7/29/2020 JEROME MAGAT PALMA
Corrections Issued 7/29/2020 JEROME MAGAT PALMA
Applicant returned to address corrections 9/24/2020 JEROME MAGAT PALMA
Plan Check Approved 10/6/2020 JEROME MAGAT PALMA
Issued 10/31/2020 APPLICANT
CofO in Progress 9/2/2022 TROY SANDERS
Permit Finaled 9/14/2022 JOHN JANSON
CofO Issued 9/14/2022 JOHN JANSON
Permit Finaled 9/14/2022 JOHN JANSON

Permit Application Clearance Information

ZI Cleared 8/20/2020 PABLO ESTRADA
Address approval Cleared 8/27/2020 GUILLERMO PETRA
Sewer availability Cleared 8/27/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 10/1/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/24/2022 Conditional Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 3/25/2022 Approved TROY SANDERS
PLUMBING-Rough 3/30/2022 Partial Approval TROY SANDERS
ELECTRICAL-Rough 4/26/2022 Approved PETER FOLLING
Gas Test 4/26/2022 Approved PETER FOLLING
Interior/Exterior Lathing 4/26/2022 Partial Approval PETER FOLLING
PLUMBING-Rough 4/26/2022 Approved PETER FOLLING
PLUMBING-Rough 4/28/2022 Partial Inspection JESUS PINEDA
Wood Frame 4/28/2022 Partial Inspection JESUS PINEDA
BUILDING-Rough-Frame 5/10/2022 Approved TROY SANDERS
Green Building Rough 5/10/2022 Approved TROY SANDERS
HVAC-Rough 5/10/2022 Approved TROY SANDERS
Insulation 5/10/2022 Approved TROY SANDERS
Drywall Nailing 5/25/2022 Approved TROY SANDERS
Shower Pan 5/25/2022 Approved TROY SANDERS
ELECTRICAL-Final 7/8/2022 Not Ready for Inspection TROY SANDERS
Final 7/8/2022 Not Ready for Inspection TROY SANDERS
Green Building Final 7/8/2022 Not Ready for Inspection TROY SANDERS
HVAC-Final 7/8/2022 Not Ready for Inspection TROY SANDERS
PLUMBING-Final 7/8/2022 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/8/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 7/8/2022 Approved TROY SANDERS
ELECTRICAL-Final 7/12/2022 Approved TROY SANDERS
Final 7/12/2022 Not Ready for Inspection TROY SANDERS
PLUMBING-Final 7/12/2022 Approved TROY SANDERS
Final 9/2/2022 OK to Issue CofO TROY SANDERS
Green Building Final 9/2/2022 Approved TROY SANDERS