22326-22328 W GILMORE ST 91303
Certificate Information: 22326-22328 W GILMORE ST 91303
- Application / Permit
- 20016-20000-17644
- Plan Check / Job No.
- B20VN09600
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT (365 SQ FT)
- Permit Issued
- Issued on 10/31/2020
- Issuing Office
- Current Status
- CofO Issued on 9/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 7/29/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 9/24/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/6/2020 | JEROME MAGAT PALMA |
| Issued | 10/31/2020 | APPLICANT |
| CofO in Progress | 9/2/2022 | TROY SANDERS |
| Permit Finaled | 9/14/2022 | JOHN JANSON |
| CofO Issued | 9/14/2022 | JOHN JANSON |
| Permit Finaled | 9/14/2022 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 8/20/2020 | PABLO ESTRADA |
| Address approval | Cleared | 8/27/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/27/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/24/2022 | Conditional Approval | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 3/25/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 3/30/2022 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 4/26/2022 | Approved | PETER FOLLING |
| Gas Test | 4/26/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 4/26/2022 | Partial Approval | PETER FOLLING |
| PLUMBING-Rough | 4/26/2022 | Approved | PETER FOLLING |
| PLUMBING-Rough | 4/28/2022 | Partial Inspection | JESUS PINEDA |
| Wood Frame | 4/28/2022 | Partial Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | TROY SANDERS |
| Green Building Rough | 5/10/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 5/10/2022 | Approved | TROY SANDERS |
| Insulation | 5/10/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 5/25/2022 | Approved | TROY SANDERS |
| Shower Pan | 5/25/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 7/8/2022 | Not Ready for Inspection | TROY SANDERS |
| Final | 7/8/2022 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 7/8/2022 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Final | 7/8/2022 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Final | 7/8/2022 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/8/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 7/8/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 7/12/2022 | Approved | TROY SANDERS |
| Final | 7/12/2022 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Final | 7/12/2022 | Approved | TROY SANDERS |
| Final | 9/2/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 9/2/2022 | Approved | TROY SANDERS |