11838 W HAMLIN ST UNIT #D 91606
Certificate Information: 11838 W HAMLIN ST UNIT #D 91606
- Application / Permit
- 20016-20000-17641
- Plan Check / Job No.
- B20VN09598
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) 31'-3" X 20'-1" IRREG SHAPED CARPORT TO ACCESSORY DWELLING UNIT (613 SQ FT).
- Permit Issued
- Issued on 10/27/2020
- Issuing Office
- Current Status
- CofO Issued on 5/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 8/2/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 10/6/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/15/2020 | JEROME MAGAT PALMA |
| Issued | 10/27/2020 | APPLICANT |
| CofO in Progress | 4/13/2021 | ROBERT DAVIS |
| Permit Finaled | 5/7/2021 | JEFFREY DURAN |
| CofO Issued | 5/7/2021 | JEFFREY DURAN |
| Permit Finaled | 5/7/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/5/2020 | GABRIEL ROBLES |
| Address approval | Cleared | 8/6/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2020 | GABRIEL ROBLES |
| Redevelopment Project Area | Cleared | 10/6/2020 | DAVID URITA |
Contact Information
| Contractor | Jb Design & Construction; Lic. No.: 469380-B | 3922 N FILION ST LOS ANGELES, CA 90065 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/20/2020 | Approved | HAMID PISHEHVAR |
| Pre-Inspection | 11/20/2020 | Approved | HAMID PISHEHVAR |
| Green Building Rough | 12/16/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 12/16/2020 | No Access for Inspection | ROBERT DAVIS |
| Green Building Rough | 1/6/2021 | Approved | ROBERT DAVIS |
| Insulation | 1/6/2021 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 1/6/2021 | SGSOV Not Ready | ROBERT DAVIS |
| Wood Frame | 1/6/2021 | Approved | ROBERT DAVIS |
| Drywall Nailing | 1/19/2021 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 1/19/2021 | Approved | ROBERT DAVIS |
| Final | 3/17/2021 | OK to Issue CofO | ROBERT DAVIS |
| Green Building Final | 3/17/2021 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 3/17/2021 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 3/17/2021 | Approved | ROBERT DAVIS |
| Final | 3/30/2021 | Not Ready for Inspection | ROBERT DAVIS |