20040-20042 W LASSEN ST 91311
Certificate Information: 20040-20042 W LASSEN ST 91311
- Application / Permit
- 20016-20000-17638
- Plan Check / Job No.
- B20VN09594
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX ATT GARAGE INTO ACCESSORY DWELLING UNIT PER ORD #186,481.
- Permit Issued
- Issued on 4/14/2021
- Issuing Office
- Current Status
- CofO Issued on 2/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 8/20/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 1/27/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 3/10/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 3/22/2021 | HAYATO TSUCHIYA |
| Issued | 4/14/2021 | APPLICANT |
| Building Plans Picked Up | 4/16/2021 | APPLICANT |
| CofO in Progress | 1/31/2022 | JEFFREY PARD |
| CofO Issued | 2/2/2022 | JOHN JANSON |
| Permit Finaled | 2/2/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/6/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/12/2021 | Partial Approval | JEFFREY PARD |
| Footing/Foundation/Slab | 8/27/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/27/2021 | Partial Approval | JEFFREY PARD |
| Sewer | 8/27/2021 | Approved | JEFFREY PARD |
| Underground Mechanical | 8/27/2021 | Corrections Issued | JEFFREY PARD |
| ELECTRICAL-Rough | 9/30/2021 | Approved | JEFFREY PARD |
| HVAC-Rough | 9/30/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 9/30/2021 | Approved | JEFFREY PARD |
| Wood Frame | 9/30/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 10/15/2021 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Approved | JEFFREY PARD |
| HVAC-Rough | 10/15/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 10/15/2021 | Approved | JEFFREY PARD |
| Wood Frame | 10/15/2021 | Approved | JEFFREY PARD |
| Insulation | 10/20/2021 | Approved | JEFFREY PARD |
| Masonry Wall/Backfill | 10/20/2021 | Not Ready for Inspection | JEFFREY PARD |
| Drywall Nailing | 10/26/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 10/26/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 10/26/2021 | Approved | JEFFREY PARD |
| Shower Pan | 10/26/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 10/29/2021 | Approved | HENRY KIM |
| Shower Pan | 10/29/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 1/28/2022 | Approved | JEFFREY PARD |
| Final | 1/28/2022 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 1/28/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 1/28/2022 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 1/28/2022 | Approved | JEFFREY PARD |