1244 S STEARNS DR 90035

Certificate Information: 1244 S STEARNS DR 90035

Application / Permit
20016-20000-17560
Plan Check / Job No.
B20VN09562
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20' X 30' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/26/2021
Issuing Office
Current Status
CofO Issued on 1/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2020 APPLICANT
Assigned to Plan Check Engineer 7/29/2020 RAPHAEL ROSAS
Corrections Issued 7/31/2020 RAPHAEL ROSAS
Plan Check Approved 1/10/2021 RAPHAEL ROSAS
Issued 1/26/2021 APPLICANT
CofO in Progress 10/20/2021 STUART CHAPMAN
Permit Finaled 1/18/2022 DEROLD HAUFF
CofO Issued 1/18/2022 DEROLD HAUFF
Permit Finaled 1/18/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/14/2020 WALLIE JONG
Sewer availability Cleared 8/14/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/17/2020 WALLIE JONG
Permit Cleared 8/17/2020 WALLIE JONG
HPOZ Cleared 9/28/2020 JONATHAN KAPLAN
ZI Cleared 9/28/2020 JONATHAN KAPLAN
Construction near power lines Cleared 12/1/2020 RIDWAN HARDY

Contact Information

Contractor Treeium Inc; Lic. No.: 617148-B 5352 LAUREL CANYON BLVD #200      VALLEY VILLAGE, CA 91607
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/23/2021 Partial Inspection ROBERT VORHIS
Footing/Foundation/Slab 3/10/2021 Partial Approval ROBERT VORHIS
Footing/Foundation/Slab 3/25/2021 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 3/25/2021 Partial Approval KATHRYN BUTTERWORTH
Sewer 3/25/2021 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 4/7/2021 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 5/13/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 5/13/2021 Approved STUART CHAPMAN
Green Building Rough 5/13/2021 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 5/13/2021 Approved STUART CHAPMAN
PLUMBING-Rough 5/13/2021 Approved STUART CHAPMAN
Underground Mechanical 5/13/2021 Not Ready for Inspection STUART CHAPMAN
Insulation 5/20/2021 Partial Inspection RUBEN SALAS
Underground Mechanical 5/20/2021 Not Ready for Inspection RUBEN SALAS
Wood Frame 5/20/2021 Partial Approval RUBEN SALAS
Interior/Exterior Lathing 5/27/2021 Partial Approval RUBEN SALAS
Wood Frame 5/27/2021 Approved RUBEN SALAS
Drywall Nailing 6/2/2021 Not Ready for Inspection SABAS ALONSO
Shower Pan 6/2/2021 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 6/8/2021 Approved SABAS ALONSO
Drywall Nailing 6/17/2021 Approved WILLIAM WREN
Interior/Exterior Lathing 6/17/2021 Approved WILLIAM WREN
Shower Pan 6/17/2021 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/4/2021 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 8/4/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 8/4/2021 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 8/4/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 8/4/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Final 8/4/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 8/4/2021 Approved KATHRYN BUTTERWORTH
Final 8/16/2021 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 8/16/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 8/16/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
ELECTRICAL-Final 9/23/2021 Not Ready for Inspection STUART CHAPMAN
Final 9/23/2021 Corrections Issued STUART CHAPMAN
Green Building Final 9/23/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Final 9/23/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 9/23/2021 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 9/23/2021 SGSOV Approved STUART CHAPMAN
ELECTRICAL-Final 10/7/2021 Not Ready for Inspection JUSTIN HAWLEY
Final 10/7/2021 Corrections Issued JUSTIN HAWLEY
Green Building Final 10/7/2021 Approved JUSTIN HAWLEY
HVAC-Final 10/7/2021 Approved JUSTIN HAWLEY
PLUMBING-Final 10/7/2021 Approved JUSTIN HAWLEY
ELECTRICAL-Final 10/20/2021 Approved STUART CHAPMAN
Final 10/20/2021 OK to Issue CofO STUART CHAPMAN