11448-11450 N GERALD AVE 91344
Certificate Information: 11448-11450 N GERALD AVE 91344
- Application / Permit
- 20016-20000-17464
- Plan Check / Job No.
- B20VN09524
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE 6'-0" X 6'-6" PORTION OF (E) FRONT PORCH TO EXTEND (E) ENTRY, CONVERT (E) 20'-0" X 22'-6" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT, REPLACE ALL (E) WINDOWS/DOOR (SAME SIZE/LOCATION), RELOCATE (E) WATER HEATER. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/14/2020
- Issuing Office
- Current Status
- CofO Issued on 6/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2020 | JENNIFER LEE |
| Corrections Issued | 7/22/2020 | JENNIFER LEE |
| Plan Check Approved | 9/14/2020 | JENNIFER LEE |
| Issued | 9/14/2020 | APPLICANT |
| CofO in Progress | 5/29/2026 | CHRISTOPHER ROJAS |
| CofO Issued | 6/30/2026 | RUBEN SALAS |
| Permit Finaled | 6/30/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/6/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2020 | GABRIEL ROBLES |
| ZA Case | Cleared | 8/21/2020 | LAUREN PADICK |
| Grading Pre-Inspection | Cleared | 8/31/2020 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shagirian,, Ashot; Lic. No.: C79415 | 11337 RUNNYMEDE ST SUN VALLEY, CA 91352 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/5/2021 | Partial Inspection | MARK JOHNSON |
| Wood Frame | 7/8/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/31/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 8/31/2021 | Partial Approval | MARK JOHNSON |
| Sewer | 8/31/2021 | Approved | MARK JOHNSON |
| Wood Frame | 9/14/2021 | Approved | MARK JOHNSON |
| Rough-Elec/Plmb/HVAC | 9/16/2021 | Partial Approval | MARK JOHNSON |
| Insulation | 9/20/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/24/2021 | Not Ready for Inspection | MARK JOHNSON |
| Drywall Nailing | 9/29/2021 | Partial Approval | MARK JOHNSON |
| ELECTRICAL-Rough | 10/5/2021 | Partial Approval | MARK JOHNSON |
| Wood Frame | 10/7/2021 | Partial Approval | MARK JOHNSON |
| PLUMBING-Final | 1/25/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 1/29/2024 | Approved | JAVIER RAMOS JR |
| Wood Frame | 1/29/2024 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/1/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 2/1/2024 | Approved | JAVIER RAMOS JR |
| Wood Frame | 2/7/2024 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 7/11/2024 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 7/11/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 8/12/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/12/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 8/13/2024 | Partial Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/11/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/11/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 3/11/2025 | Partial Inspection | JAVIER RAMOS JR |
| Final | 3/11/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 3/11/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 3/11/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 3/11/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 3/11/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/11/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 3/11/2025 | Approved | JAVIER RAMOS JR |
| Final | 3/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 3/20/2025 | Approved | JENNIFER RABUCHIN |
| Final | 5/22/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 5/28/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 5/29/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 5/29/2026 | Approved | CHRISTOPHER ROJAS |