CONVERT THE (E) 16'1" x 19'7" GARAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP
Permit Issued
Issued on 9/18/2020
Issuing Office
Current Status
CofO Issued on 2/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 MOHAMMAD ESMAILI
Corrections Issued 7/25/2020 MOHAMMAD ESMAILI
Applicant returned to address corrections 7/26/2020 MOHAMMAD ESMAILI
Building Plans Picked Up 7/27/2020 APPLICANT
Issued 9/18/2020 APPLICANT
CofO in Progress 2/1/2021 MICHEL ABAJAN
Permit Finaled 2/20/2021 MICHAEL SMITH
CofO Issued 2/20/2021 MICHAEL SMITH
Permit Finaled 2/20/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/27/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/27/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 7/27/2020 GABRIEL ROBLES
Sewer availability Cleared 7/27/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/30/2020 Not Ready for Inspection WILLIAM KUEHN
Pre-Inspection 9/30/2020 Partial Inspection WILLIAM KUEHN
Sewer 9/30/2020 Not Ready for Inspection WILLIAM KUEHN
Gas Test 10/22/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 10/22/2020 Not Ready for Inspection JOHN HAYES
Sewer 10/22/2020 Not Ready for Inspection JOHN HAYES
Gas Test 10/30/2020 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 10/30/2020 Partial Approval JENNIFER RABUCHIN
Sewer 10/30/2020 Approved JENNIFER RABUCHIN
Wood Frame 10/30/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/9/2020 Not Ready for Inspection WILLIAM KUEHN
HVAC-Rough 11/9/2020 Not Ready for Inspection WILLIAM KUEHN
Wood Frame 11/9/2020 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 11/17/2020 Not Ready for Inspection DANIEL DREW
Gas Test 11/17/2020 Approved DANIEL DREW
Green Building Rough 11/17/2020 Approved DANIEL DREW
Rough-Elec/Plmb/HVAC 11/17/2020 Approved DANIEL DREW
Wood Frame 11/17/2020 Partial Inspection DANIEL DREW
Drywall Nailing 11/24/2020 Corrections Issued JENNIFER RABUCHIN
Insulation 11/24/2020 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 12/1/2020 Approved JENNIFER RABUCHIN
Insulation 12/1/2020 Approved JENNIFER RABUCHIN
Shower Pan 12/1/2020 Approved JENNIFER RABUCHIN
Green Building Final 12/8/2020 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 12/8/2020 Approved MICHEL ABAJAN
Pre-Inspection 12/8/2020 Partial Approval MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/8/2020 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 12/8/2020 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 1/5/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/5/2021 Corrections Issued JENNIFER RABUCHIN
Final 1/5/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/5/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 1/5/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/5/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 1/5/2021 Approved JENNIFER RABUCHIN
Final 1/22/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/22/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 2/1/2021 Approved MICHEL ABAJAN
Final 2/1/2021 OK to Issue CofO MICHEL ABAJAN
Green Building Final 2/1/2021 Approved MICHEL ABAJAN
HVAC-Final 2/1/2021 Approved MICHEL ABAJAN
PLUMBING-Final 2/1/2021 Approved MICHEL ABAJAN