6846-6848 N COSTELLO AVE 91405
Certificate Information: 6846-6848 N COSTELLO AVE 91405
- Application / Permit
- 20016-20000-17087
- Plan Check / Job No.
- B20VN09383
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) 16'1" x 19'7" GARAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP
- Permit Issued
- Issued on 9/18/2020
- Issuing Office
- Current Status
- CofO Issued on 2/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 7/25/2020 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 7/26/2020 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 7/27/2020 | APPLICANT |
| Issued | 9/18/2020 | APPLICANT |
| CofO in Progress | 2/1/2021 | MICHEL ABAJAN |
| Permit Finaled | 2/20/2021 | MICHAEL SMITH |
| CofO Issued | 2/20/2021 | MICHAEL SMITH |
| Permit Finaled | 2/20/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 7/27/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/27/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/30/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Pre-Inspection | 9/30/2020 | Partial Inspection | WILLIAM KUEHN |
| Sewer | 9/30/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Gas Test | 10/22/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 10/22/2020 | Not Ready for Inspection | JOHN HAYES |
| Sewer | 10/22/2020 | Not Ready for Inspection | JOHN HAYES |
| Gas Test | 10/30/2020 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/30/2020 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 10/30/2020 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 10/30/2020 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/9/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| HVAC-Rough | 11/9/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Wood Frame | 11/9/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 11/17/2020 | Not Ready for Inspection | DANIEL DREW |
| Gas Test | 11/17/2020 | Approved | DANIEL DREW |
| Green Building Rough | 11/17/2020 | Approved | DANIEL DREW |
| Rough-Elec/Plmb/HVAC | 11/17/2020 | Approved | DANIEL DREW |
| Wood Frame | 11/17/2020 | Partial Inspection | DANIEL DREW |
| Drywall Nailing | 11/24/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 11/24/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 12/1/2020 | Approved | JENNIFER RABUCHIN |
| Insulation | 12/1/2020 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 12/1/2020 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 12/8/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/8/2020 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 12/8/2020 | Partial Approval | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2020 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 12/8/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/5/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/5/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/5/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/5/2021 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 1/5/2021 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/5/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/5/2021 | Approved | JENNIFER RABUCHIN |
| Final | 1/22/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/22/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/1/2021 | Approved | MICHEL ABAJAN |
| Final | 2/1/2021 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 2/1/2021 | Approved | MICHEL ABAJAN |
| HVAC-Final | 2/1/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 2/1/2021 | Approved | MICHEL ABAJAN |