20301-20301 1/2 W VOSE ST 91306
Certificate Information: 20301-20301 1/2 W VOSE ST 91306
- Application / Permit
- 20016-20000-16821
- Plan Check / Job No.
- B20VN09268
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/20/2020
- Issuing Office
- Current Status
- CofO Issued on 5/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2020 | AMIR DANAI |
| Corrections Issued | 9/1/2020 | AMIR DANAI |
| Issued | 10/20/2020 | APPLICANT |
| CofO in Progress | 5/10/2021 | HENRY KIM |
| Permit Finaled | 5/11/2021 | JOHN JANSON |
| CofO Issued | 5/11/2021 | JOHN JANSON |
| Permit Finaled | 5/11/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 9/17/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 9/17/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 9/17/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | I Team Builders And Design Inc; Lic. No.: 1029756-B | 22647 VENTURA BLVD #265 WOODLAND HILLS, CA 91364 |
| Engineer | Hajdari,, Genti; Lic. No.: C88031 | 140 S MENTOR AVE APT #207 PASADENA, CA 91106 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/22/2020 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 12/22/2020 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 12/22/2020 | Partial Approval | JEFFREY PARD |
| Underground Mechanical | 12/22/2020 | Partial Approval | JEFFREY PARD |
| BUILDING-Rough-Frame | 12/31/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 12/31/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 12/31/2020 | Corrections Issued | HENRY KIM |
| Pre-Inspection | 12/31/2020 | Corrections Issued | HENRY KIM |
| Sewer | 12/31/2020 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 12/31/2020 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 1/12/2021 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 1/12/2021 | Approved | HENRY KIM |
| Gas Test | 1/12/2021 | Partial Approval | HENRY KIM |
| HVAC-Rough | 1/12/2021 | Approved | HENRY KIM |
| PLUMBING-Rough | 1/12/2021 | Approved | HENRY KIM |
| Sewer | 1/12/2021 | Approved | HENRY KIM |
| Underground Mechanical | 1/12/2021 | Partial Approval | HENRY KIM |
| Insulation | 1/14/2021 | Approved | HENRY KIM |
| Shower Pan | 1/14/2021 | Approved | HENRY KIM |
| Deputy Drilled-In Anchors | 1/19/2021 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2021 | Approved | HENRY KIM |
| Drywall Nailing | 1/22/2021 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 1/22/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 4/9/2021 | Not Ready for Inspection | HENRY KIM |
| Final | 4/9/2021 | Not Ready for Inspection | HENRY KIM |
| Green Building Final | 4/9/2021 | Not Ready for Inspection | HENRY KIM |
| Green Building Rough | 4/9/2021 | Not Ready for Inspection | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 4/9/2021 | SGSOV Not Ready | HENRY KIM |
| Smoke Detectors | 4/9/2021 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 4/16/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 4/16/2021 | Corrections Issued | HENRY KIM |
| Final | 4/16/2021 | Corrections Issued | HENRY KIM |
| Green Building Final | 4/16/2021 | Approved | HENRY KIM |
| Green Building Rough | 4/16/2021 | Approved | HENRY KIM |
| HVAC-Final | 4/16/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 4/16/2021 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 4/16/2021 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 4/16/2021 | Approved | HENRY KIM |
| Underground Mechanical | 4/16/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 5/10/2021 | Approved | HENRY KIM |
| Final | 5/10/2021 | OK to Issue CofO | HENRY KIM |
| HVAC-Final | 5/10/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 5/10/2021 | Approved | HENRY KIM |