11747-11749 N CHIVERS AVE 91331
Certificate Information: 11747-11749 N CHIVERS AVE 91331
- Application / Permit
- 20016-20000-16794
- Plan Check / Job No.
- B20VN09258
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 19' X 19' ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER WFPP. "COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 4/8/820. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 8/20/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/30/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2020 | JENNIFER LEE |
| Corrections Issued | 7/23/2020 | JENNIFER LEE |
| Plan Check Approved | 8/10/2020 | SINA KHOSRAVI |
| Issued | 8/20/2020 | APPLICANT |
| CofO in Progress | 11/12/2020 | MICHEL ABAJAN |
| CofO Issued | 12/30/2020 | MICHAEL SMITH |
| Permit Finaled | 12/30/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/27/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Ultimate Green Construction Inc; Lic. No.: 1023605-B | 13302 FILMORE ST PACOIMA, CA 91331 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/2/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/16/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/16/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/16/2020 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 9/16/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/16/2020 | Approved | MICHEL ABAJAN |
| Insulation | 9/21/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/21/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 9/25/2020 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 10/19/2020 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/4/2020 | Approved | MICHEL ABAJAN |
| Final | 11/4/2020 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 11/4/2020 | Approved | MICHEL ABAJAN |
| HVAC-Final | 11/4/2020 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 11/4/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/4/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2020 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 11/4/2020 | Approved | MICHEL ABAJAN |
| Final | 11/12/2020 | OK to Issue CofO | MICHEL ABAJAN |