11747-11749 N CHIVERS AVE 91331

Certificate Information: 11747-11749 N CHIVERS AVE 91331

Application / Permit
20016-20000-16794
Plan Check / Job No.
B20VN09258
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 19' X 19' ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER WFPP. "COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 4/8/820. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
Permit Issued
Issued on 8/20/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/30/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 7/22/2020 JENNIFER LEE
Corrections Issued 7/23/2020 JENNIFER LEE
Plan Check Approved 8/10/2020 SINA KHOSRAVI
Issued 8/20/2020 APPLICANT
CofO in Progress 11/12/2020 MICHEL ABAJAN
CofO Issued 12/30/2020 MICHAEL SMITH
Permit Finaled 12/30/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/27/2020 ADRIAN CASTRO
Sewer availability Cleared 7/27/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/28/2020 ADRIAN CASTRO

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B 13302 FILMORE ST      PACOIMA, CA 91331

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/2/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/16/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 9/16/2020 Approved MICHEL ABAJAN
Green Building Rough 9/16/2020 Approved MICHEL ABAJAN
MERV13>=Rough 9/16/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 9/16/2020 Approved MICHEL ABAJAN
Insulation 9/21/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/21/2020 Approved MICHEL ABAJAN
Drywall Nailing 9/25/2020 Approved MICHEL ABAJAN
Underground Mechanical 10/19/2020 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 11/4/2020 Approved MICHEL ABAJAN
Final 11/4/2020 Corrections Issued MICHEL ABAJAN
Green Building Final 11/4/2020 Approved MICHEL ABAJAN
HVAC-Final 11/4/2020 Approved MICHEL ABAJAN
MERV13>=Final 11/4/2020 Approved MICHEL ABAJAN
PLUMBING-Final 11/4/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/4/2020 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 11/4/2020 Approved MICHEL ABAJAN
Final 11/12/2020 OK to Issue CofO MICHEL ABAJAN