9428-9430 N GLADE AVE 91311
Certificate Information: 9428-9430 N GLADE AVE 91311
- Application / Permit
- 20016-20000-16611
- Plan Check / Job No.
- B20VN09190
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ATTACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PERLAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 10/1/2020
- Issuing Office
- Current Status
- CofO Issued on 4/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2020 | SELLA BENYAMIN |
| Corrections Issued | 7/23/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 7/27/2020 | APPLICANT |
| Plan Check Approved | 9/21/2020 | SELLA BENYAMIN |
| Issued | 10/1/2020 | APPLICANT |
| CofO in Progress | 4/15/2021 | DAVID STEPANYAN |
| Permit Finaled | 4/16/2021 | JOHN JANSON |
| CofO Issued | 4/16/2021 | JOHN JANSON |
| Permit Finaled | 4/16/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/13/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/13/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 8/26/2020 | BARTON HOLMES |
| Specific Plan | Cleared | 9/14/2020 | WILLIAM CABRERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/12/2020 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 11/14/2020 | Approved | TROY SANDERS |
| PLUMBING-Rough | 11/14/2020 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 12/8/2020 | Corrections Issued | DAVID STEPANYAN |
| FLOOD-Proofing Certificate | 12/8/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 12/8/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 12/8/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Special/Order Compliance | 12/8/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 12/15/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 12/15/2020 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 12/15/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Rough | 12/15/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 12/15/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 12/15/2020 | Corrections Issued | DAVID STEPANYAN |
| Special/Order Compliance | 12/17/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 12/21/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 12/21/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Final | 12/21/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 12/21/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 2/1/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 2/1/2021 | Approved | DAVID STEPANYAN |
| Green Building Rough | 2/1/2021 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 2/1/2021 | Approved | DAVID STEPANYAN |
| Special/Order Compliance | 2/1/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Final | 4/5/2021 | Corrections Issued | DAVID STEPANYAN |
| Final | 4/5/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Final | 4/5/2021 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Final | 4/5/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Final | 4/5/2021 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Approved | DAVID STEPANYAN |
| Smoke Detectors | 4/5/2021 | Approved | DAVID STEPANYAN |
| Special/Order Compliance | 4/5/2021 | Partial Inspection | DAVID STEPANYAN |
| ELECTRICAL-Final | 4/14/2021 | Approved | DAVID STEPANYAN |
| Final | 4/14/2021 | OK to Issue CofO | DAVID STEPANYAN |
| Gas Test | 4/14/2021 | Approved | DAVID STEPANYAN |
| Green Building Final | 4/14/2021 | Approved | DAVID STEPANYAN |
| HVAC-Final | 4/14/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 4/14/2021 | Approved | DAVID STEPANYAN |