10769 W ADDISON ST 91601
Certificate Information: 10769 W ADDISON ST 91601
- Application / Permit
- 20016-20000-16562
- Plan Check / Job No.
- X20VN08284
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Kitchen (3)/bathroom (3) remodel for residential buildings (no structural changes). Window (21) and door (3) change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council (NFRC), is required for doors and windows replaced in all residential buildings, three stories or less, per Section 150.2(b)1B of Title 24. Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over new solid sheathing (30) squares. For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roofing Rating Council (CRRC). Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0(b)2B. Fiber Cement siding over solid sheathing with an approved water resistive barrier per valid ICC Evaluation Report #ESR 2290 on exterior walls at 5 feet or more from property lines for residential buildings. (Applicant to provide a copy of the report to inspector).
- Permit Issued
- Issued on 8/17/2020
- Issuing Office
- Current Status
- Permit Finaled on 4/28/2021
Permit Application Status History
| No Progress | 7/13/2020 | BLANCA MORALES |
| Issued | 8/17/2020 | APPLICANT |
| Permit Finaled | 4/28/2021 | HAMID PISHEHVAR |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 7/16/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 8/11/2020 | MICAELA TORRES-GIL |
Contact Information
| Contractor | Nest Interiors Inc; Lic. No.: 1033348-B | 530 S LAKE AVE SUITE 271N PASADENA, CA 91101 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2020 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 10/20/2020 | Partial Approval | ROBERT DAVIS |
| Wood Frame | 10/20/2020 | Approved | ROBERT DAVIS |
| Drywall Nailing | 10/30/2020 | Approved | ROBERT DAVIS |
| Insulation | 10/30/2020 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 11/4/2020 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 3/30/2021 | SGSOV Not Ready | ROBERT DAVIS |
| Final | 4/28/2021 | Permit Finaled | HAMID PISHEHVAR |
| SGSOV-Seismic Gas S/O Valve | 4/28/2021 | SGSOV Approved | HAMID PISHEHVAR |
| Smoke Detectors | 4/28/2021 | Approved | HAMID PISHEHVAR |