Permit Issued
Issued on 9/23/2020
Issuing Office
Current Status
CofO Issued on 12/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2020 APPLICANT
Assigned to Plan Check Engineer 7/21/2020 SERGIO MUNIZ
Corrections Issued 7/22/2020 SERGIO MUNIZ
Building Plans Picked Up 7/24/2020 APPLICANT
Applicant returned to address corrections 9/16/2020 SERGIO MUNIZ
Plan Check Approved 9/22/2020 SERGIO MUNIZ
Issued 9/23/2020 APPLICANT
CofO in Progress 12/10/2024 JAVIER RAMOS JR
Permit Finaled 12/19/2024 RUBEN SALAS
CofO Issued 12/19/2024 RUBEN SALAS
Permit Finaled 12/19/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/27/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 7/27/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 7/27/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 8/11/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/25/2021 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 5/25/2021 Corrections Issued MICHAEL TEMPLE
Sewer 5/25/2021 Corrections Issued MICHAEL TEMPLE
Underground Mechanical 5/25/2021 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 11/29/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 11/29/2021 Corrections Issued MARK JOHNSON
Sewer 11/29/2021 Approved MARK JOHNSON
Underground Mechanical 11/29/2021 Approved MARK JOHNSON
Deputy Drilled-In Anchors 12/13/2021 Conditional Approval MARK JOHNSON
Deputy Drilled-In Anchors 12/15/2021 Conditional Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 12/21/2021 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 3/18/2022 Approved RAUL OLAGI
PLUMBING-Rough 3/18/2022 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 11/1/2022 Approved JAVIER RAMOS JR
Insulation 11/1/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 11/1/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 11/28/2022 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 11/28/2022 Approved JAVIER RAMOS JR
Insulation 11/28/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 11/28/2022 Partial Approval JAVIER RAMOS JR
Wood Frame 11/28/2022 Approved JAVIER RAMOS JR
Drywall Nailing 12/30/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 12/30/2022 Approved JAVIER RAMOS JR
Green Building Rough 12/30/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/30/2022 Approved JAVIER RAMOS JR
Pre-Inspection 12/30/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 9/30/2024 Approved KEVIN BERBERYAN
Final 9/30/2024 Corrections Issued KEVIN BERBERYAN
Green Building Final 9/30/2024 Not Ready for Inspection KEVIN BERBERYAN
MERV13>=Final 9/30/2024 Approved KEVIN BERBERYAN
MERV13>=Rough 9/30/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 9/30/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 12/6/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 12/6/2024 Approved JAVIER RAMOS JR
Service/Power Release 12/6/2024 Approved JAVIER RAMOS JR
Smoke Detectors 12/6/2024 Approved JAVIER RAMOS JR