7407-7409 N PEACH AVE 91406

Certificate Information: 7407-7409 N PEACH AVE 91406

Application / Permit
20016-20000-16537
Plan Check / Job No.
B20VN09149
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 19'-8" X 17'-5" ATTACHED GARAGE AND 25'-9" X 17'-1" IRREGULAR SHAPED PORTION OF DWELLING TO NEW ACCESSORY DWELLING UNIT
Permit Issued
Issued on 9/20/2020
Issuing Office
Current Status
CofO Issued on 5/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 SELLA BENYAMIN
Corrections Issued 7/24/2020 SELLA BENYAMIN
Building Plans Picked Up 7/27/2020 APPLICANT
Plan Check Approved 8/18/2020 SELLA BENYAMIN
Issued 9/20/2020 APPLICANT
CofO in Progress 2/25/2021 GREGG CUMMINGS
CofO in Progress 3/4/2021 GREGG CUMMINGS
CofO in Progress 4/12/2021 DAVID MATSON
CofO Issued 5/15/2021 MICHAEL SMITH
Permit Finaled 5/15/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/30/2020 GUILLERMO PETRA
Sewer availability Cleared 7/30/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 8/4/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/29/2020 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 11/2/2020 Corrections Issued GREGG CUMMINGS
Pre-Inspection 11/2/2020 Partial Approval GREGG CUMMINGS
Footing/Foundation/Slab 11/6/2020 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 12/9/2020 Approved GREGG CUMMINGS
ELECTRICAL-Rough 12/9/2020 Approved GREGG CUMMINGS
Green Building Rough 12/9/2020 Approved GREGG CUMMINGS
Insulation 12/9/2020 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 12/9/2020 Approved GREGG CUMMINGS
Insulation 12/16/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 12/16/2020 Approved GREGG CUMMINGS
Shower Pan 12/16/2020 Approved GREGG CUMMINGS
Drywall Nailing 12/22/2020 Approved GREGG CUMMINGS
ELECTRICAL-Final 2/2/2021 Corrections Issued GREGG CUMMINGS
Final 2/2/2021 Corrections Issued GREGG CUMMINGS
Green Building Final 2/2/2021 Corrections Issued GREGG CUMMINGS
HVAC-Final 2/2/2021 Corrections Issued GREGG CUMMINGS
PLUMBING-Final 2/2/2021 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 2/2/2021 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 2/2/2021 Approved GREGG CUMMINGS
ELECTRICAL-Final 2/25/2021 Approved GREGG CUMMINGS
Final 2/25/2021 Partial Inspection GREGG CUMMINGS
Green Building Final 2/25/2021 Approved GREGG CUMMINGS
HVAC-Final 2/25/2021 Approved GREGG CUMMINGS
PLUMBING-Final 2/25/2021 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 2/25/2021 SGSOV Approved GREGG CUMMINGS
Final 3/4/2021 Corrections Issued GREGG CUMMINGS
Final 4/12/2021 OK to Issue CofO DAVID MATSON