7407-7409 N PEACH AVE 91406
Certificate Information: 7407-7409 N PEACH AVE 91406
- Application / Permit
- 20016-20000-16537
- Plan Check / Job No.
- B20VN09149
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 19'-8" X 17'-5" ATTACHED GARAGE AND 25'-9" X 17'-1" IRREGULAR SHAPED PORTION OF DWELLING TO NEW ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 9/20/2020
- Issuing Office
- Current Status
- CofO Issued on 5/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | SELLA BENYAMIN |
| Corrections Issued | 7/24/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 7/27/2020 | APPLICANT |
| Plan Check Approved | 8/18/2020 | SELLA BENYAMIN |
| Issued | 9/20/2020 | APPLICANT |
| CofO in Progress | 2/25/2021 | GREGG CUMMINGS |
| CofO in Progress | 3/4/2021 | GREGG CUMMINGS |
| CofO in Progress | 4/12/2021 | DAVID MATSON |
| CofO Issued | 5/15/2021 | MICHAEL SMITH |
| Permit Finaled | 5/15/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/30/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/29/2020 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2020 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/2/2020 | Corrections Issued | GREGG CUMMINGS |
| Pre-Inspection | 11/2/2020 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/6/2020 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/9/2020 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/9/2020 | Approved | GREGG CUMMINGS |
| Green Building Rough | 12/9/2020 | Approved | GREGG CUMMINGS |
| Insulation | 12/9/2020 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 12/9/2020 | Approved | GREGG CUMMINGS |
| Insulation | 12/16/2020 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/16/2020 | Approved | GREGG CUMMINGS |
| Shower Pan | 12/16/2020 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 12/22/2020 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/2/2021 | Corrections Issued | GREGG CUMMINGS |
| Final | 2/2/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/2/2021 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Final | 2/2/2021 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Final | 2/2/2021 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/2/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 2/2/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/25/2021 | Approved | GREGG CUMMINGS |
| Final | 2/25/2021 | Partial Inspection | GREGG CUMMINGS |
| Green Building Final | 2/25/2021 | Approved | GREGG CUMMINGS |
| HVAC-Final | 2/25/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 2/25/2021 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/25/2021 | SGSOV Approved | GREGG CUMMINGS |
| Final | 3/4/2021 | Corrections Issued | GREGG CUMMINGS |
| Final | 4/12/2021 | OK to Issue CofO | DAVID MATSON |