4401 S CRENSHAW BLVD 90008

Certificate Information: 4401 S CRENSHAW BLVD 90008

Application / Permit
20016-20000-16204
Plan Check / Job No.
B20VN08966
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Bank
Work Description
TENANT IMPROVEMENT OF (E) 1ST STORY BANK IN 3 STORY OFFICE BUILDING, ADD 12 HVAC UNITS ON ROOFTOP (4) UNITS AT 250 LBS EACH , (6) UNITS AT 200 LBS EACH , (1) UNITS AT 300 LBS EACH , (1) UNIT AT 350 LBS EACH , ALL WORK PER ENGINEERING - SEE COMMENTS
Permit Issued
Issued on 11/13/2020
Issuing Office
Current Status
Permit Finaled on 4/26/2021

Permit Application Status History

Submitted 7/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 RARES BODEA
Corrections Issued 8/17/2020 RARES BODEA
Quality Review Completed 8/18/2020 STEVEN KIM
Building Plans Picked Up 8/24/2020 APPLICANT
Disabled Access Plans Picked Up 8/24/2020 APPLICANT
Green Plans Picked Up 8/24/2020 APPLICANT
Applicant returned to address corrections 10/30/2020 RARES BODEA
Plan Check Approved 11/13/2020 RARES BODEA
Issued 11/13/2020 APPLICANT
Permit Finaled 4/23/2021 LANNY MERRICK

Permit Application Clearance Information

Green Code Cleared 9/24/2020 AARON COSTA
DAS Clearance Cleared 10/1/2020 NORLITO MEDRANO
"D" conditions Cleared 10/2/2020 MIGUEL GAMBOA
Specific Plan Cleared 10/2/2020 MIGUEL GAMBOA
ZI Cleared 10/2/2020 MIGUEL GAMBOA
Redevelopment Project Area Cleared 10/19/2020 DAVID URITA
Metro Rail approval Cleared 11/10/2020 RARES BODEA

Contact Information

Architect Siros,, Anthony J; Lic. No.: C11497 17025 E LA MONTANA DRIVE UNIT 132      FOUNTAIN HILLS, AZ 85268
Contractor Frans Construction Inc; Lic. No.: 597405-B 335 S EDGEWOOD LN STE 100      EAGLE, ID 83616
Engineer Furstenau,, Devon W; Lic. No.: S3626 1508 E LELAND      MESA, AZ 85203

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 11/20/2020 Partial Approval LEOPOLDO MENDOZA
Light Gage Steel Frame 11/20/2020 Partial Approval LEOPOLDO MENDOZA
Drywall Nailing 11/30/2020 Partial Approval LEOPOLDO MENDOZA
Light Gage Steel Frame 11/30/2020 Partial Approval LEOPOLDO MENDOZA
Insulation 12/3/2020 Partial Approval LEOPOLDO MENDOZA
Drywall Nailing 12/4/2020 Partial Approval LEOPOLDO MENDOZA
Light Gage Steel Frame 1/6/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Steel/Welding 1/8/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Steel/Welding 1/13/2021 Conditional Approval RUSSELL BONVOULOIR
Drywall Nailing 1/15/2021 Partial Approval LEOPOLDO MENDOZA
Light Gage Steel Frame 1/20/2021 Partial Approval LANNY MERRICK
Drywall Nailing 1/29/2021 Approved LANNY MERRICK
T-Bar Ceiling 2/4/2021 Not Ready for Inspection LANNY MERRICK
Final 4/23/2021 Permit Finaled LANNY MERRICK
Green Building Final 4/23/2021 Approved LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 4/23/2021 SGSOV Approved LANNY MERRICK
Smoke Detectors 4/23/2021 Approved LANNY MERRICK