8325 W DAY ST 91040

Certificate Information: 8325 W DAY ST 91040

Application / Permit
20016-20000-16178
Plan Check / Job No.
B20VN08958
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'10" X 18'5" DETACHED ACCESSORY DWELLING UNIT AS PER GCS 65852.2(E)(1)(B) , ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/24/2021
Issuing Office
Current Status
CofO Issued on 11/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/15/2020 RARES BODEA
Corrections Issued 7/15/2020 RARES BODEA
Building Plans Picked Up 7/16/2020 APPLICANT
Applicant returned to address corrections 8/12/2020 RARES BODEA
Applicant returned to address corrections 5/16/2021 RARES BODEA
Plan Check Approved 5/20/2021 RARES BODEA
Issued 5/24/2021 APPLICANT
CofO in Progress 10/7/2024 DAVID ANDERSON
Permit Finaled 11/2/2024 DANIEL ORRANTE
CofO Issued 11/2/2024 DANIEL ORRANTE
Permit Finaled 11/2/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/14/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/14/2020 ADRIAN CASTRO
Sewer availability Cleared 10/14/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 10/16/2020 MATTHEW CRAIG
Construction near power lines Cleared 12/24/2020 RIDWAN HARDY
Construction within easement Cleared 12/24/2020 RIDWAN HARDY
Low Impact Development Cleared 4/15/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 4/16/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 5/14/2021 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng David; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/8/2021 Corrections Issued MATTHEW NELSON
Pre-Inspection 6/29/2021 Partial Inspection MATTHEW NELSON
Pre-Inspection 10/20/2023 Approved DAVID ANDERSON
Deputy Drilled-In Anchors 2/20/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 2/23/2024 Approved DAVID ANDERSON
Special/Order Compliance 2/23/2024 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 5/14/2024 Approved DAVID ANDERSON
Green Building Rough 5/14/2024 Approved DAVID ANDERSON
HVAC-Rough 5/14/2024 Approved DAVID ANDERSON
PLUMBING-Rough 5/14/2024 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 5/14/2024 Approved DAVID ANDERSON
Deputy Wood Construction 5/15/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 5/17/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 5/17/2024 Approved DAVID ANDERSON
Shower Pan 5/17/2024 Approved DAVID ANDERSON
Insulation 5/29/2024 No Access for Inspection DAVID ANDERSON
Interior/Exterior Lathing 5/29/2024 No Access for Inspection DAVID ANDERSON
Insulation 6/3/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/3/2024 Partial Approval DAVID ANDERSON
Drywall Nailing 6/10/2024 Approved DAVID ANDERSON
Final 8/26/2024 Corrections Issued DAVID ANDERSON
Green Building Final 8/26/2024 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Not Ready DAVID ANDERSON
Service/Power Release 8/26/2024 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 8/26/2024 Approved DAVID ANDERSON
Final 10/4/2024 OK to Issue CofO DAVID ANDERSON
Green Building Final 10/4/2024 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/4/2024 SGSOV Approved DAVID ANDERSON
Service/Power Release 10/4/2024 Approved DAVID ANDERSON