7901-7903 S HULBERT AVE 90293
Certificate Information: 7901-7903 S HULBERT AVE 90293
- Application / Permit
- 20016-20000-15918
- Plan Check / Job No.
- B20VN08871
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) under floor area to (N) adu of (E) sfd w/ garage. all work per engineer
- Permit Issued
- Issued on 4/6/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2020 | PINANK PATEL |
| Corrections Issued | 7/29/2020 | PINANK PATEL |
| Applicant returned to address corrections | 12/11/2020 | PINANK PATEL |
| Plan Check Approved | 3/8/2021 | PINANK PATEL |
| Building Plans Picked Up | 3/9/2021 | APPLICANT |
| Issued | 4/6/2021 | APPLICANT |
| CofO in Progress | 11/17/2021 | RICHARD STEINBACH |
| Permit Finaled | 11/18/2021 | DANIEL ORRANTE |
| CofO Issued | 11/18/2021 | DANIEL ORRANTE |
| Permit Finaled | 11/18/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 2/23/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/9/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Pre-Inspection | 4/12/2021 | Corrections Issued | BRENDAN LOONEY |
| Underground Mechanical | 6/7/2021 | Corrections Issued | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 6/9/2021 | Conditional Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 6/11/2021 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 6/24/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 6/24/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 6/24/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| METHANE-Rough | 6/24/2021 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 6/24/2021 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/19/2021 | Corrections Issued | BRENDAN LOONEY |
| METHANE-Rough | 7/19/2021 | Approved | BRENDAN LOONEY |
| Rough-Elec/Plmb/HVAC | 7/19/2021 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/2/2021 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 8/2/2021 | Approved | BRENDAN LOONEY |
| Green Building Rough | 8/2/2021 | Approved | BRENDAN LOONEY |
| HVAC-Rough | 8/2/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 8/2/2021 | Partial Approval | BRENDAN LOONEY |
| Insulation | 8/12/2021 | Partial Approval | BRENDAN LOONEY |
| Insulation | 8/16/2021 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 8/19/2021 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/1/2021 | Approved | BRENDAN LOONEY |
| Final | 10/1/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 10/1/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 10/1/2021 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 10/1/2021 | Approved | BRENDAN LOONEY |
| Final | 10/8/2021 | OK to Issue CofO | BRENDAN LOONEY |
| Green Building Final | 10/8/2021 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 10/8/2021 | SGSOV Approved | BRENDAN LOONEY |