7901-7903 S HULBERT AVE 90293

Certificate Information: 7901-7903 S HULBERT AVE 90293

Application / Permit
20016-20000-15918
Plan Check / Job No.
B20VN08871
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert (E) under floor area to (N) adu of (E) sfd w/ garage. all work per engineer
Permit Issued
Issued on 4/6/2021
Issuing Office
Valley
Current Status
CofO Issued on 11/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2020 APPLICANT
Assigned to Plan Check Engineer 7/6/2020 PINANK PATEL
Corrections Issued 7/29/2020 PINANK PATEL
Applicant returned to address corrections 12/11/2020 PINANK PATEL
Plan Check Approved 3/8/2021 PINANK PATEL
Building Plans Picked Up 3/9/2021 APPLICANT
Issued 4/6/2021 APPLICANT
CofO in Progress 11/17/2021 RICHARD STEINBACH
Permit Finaled 11/18/2021 DANIEL ORRANTE
CofO Issued 11/18/2021 DANIEL ORRANTE
Permit Finaled 11/18/2021 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/23/2021 ANTHONY MAINEZ
Sewer availability Cleared 2/23/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 2/24/2021 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/9/2021 Not Ready for Inspection BRENDAN LOONEY
Pre-Inspection 4/12/2021 Corrections Issued BRENDAN LOONEY
Underground Mechanical 6/7/2021 Corrections Issued BRENDAN LOONEY
Deputy Drilled-In Anchors 6/9/2021 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 6/11/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 6/24/2021 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 6/24/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 6/24/2021 Not Ready for Inspection BRENDAN LOONEY
METHANE-Rough 6/24/2021 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 6/24/2021 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 7/19/2021 Corrections Issued BRENDAN LOONEY
METHANE-Rough 7/19/2021 Approved BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 7/19/2021 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 8/2/2021 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 8/2/2021 Approved BRENDAN LOONEY
Green Building Rough 8/2/2021 Approved BRENDAN LOONEY
HVAC-Rough 8/2/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 8/2/2021 Partial Approval BRENDAN LOONEY
Insulation 8/12/2021 Partial Approval BRENDAN LOONEY
Insulation 8/16/2021 Approved BRENDAN LOONEY
Drywall Nailing 8/19/2021 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 10/1/2021 Approved BRENDAN LOONEY
Final 10/1/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 10/1/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 10/1/2021 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 10/1/2021 Approved BRENDAN LOONEY
Final 10/8/2021 OK to Issue CofO BRENDAN LOONEY
Green Building Final 10/8/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 10/8/2021 SGSOV Approved BRENDAN LOONEY