522 1/2 W 88TH ST 90044

Certificate Information: 522 1/2 W 88TH ST 90044

Application / Permit
20016-20000-15759
Plan Check / Job No.
B20VN08803
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 20'-7" X 34' REC ROOM TO NEW ACCESSORY DWELLING UNIT
Permit Issued
Issued on 9/15/2020
Issuing Office
Current Status
CofO Issued on 1/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 SELLA BENYAMIN
Corrections Issued 7/14/2020 SELLA BENYAMIN
Building Plans Picked Up 7/14/2020 APPLICANT
Plan Check Approved 9/2/2020 SELLA BENYAMIN
Issued 9/15/2020 APPLICANT
CofO in Progress 12/31/2020 ANSON MAGLASANG
Permit Finaled 1/2/2021 DEROLD HAUFF
CofO Issued 1/2/2021 DEROLD HAUFF
Permit Finaled 1/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/17/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/18/2020 WALLIE JONG
Sewer availability Cleared 8/18/2020 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/1/2020 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 10/1/2020 Approved FREDDIE RIVERA
Green Building Rough 10/1/2020 Not Ready for Inspection FREDDIE RIVERA
MERV13>=Rough 10/1/2020 Not Ready for Inspection FREDDIE RIVERA
Pre-Inspection 10/1/2020 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 10/9/2020 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 10/9/2020 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/9/2020 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 10/9/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/23/2020 Not Ready for Inspection DAVID FEILER
Final 10/23/2020 Corrections Issued DAVID FEILER
Green Building Final 10/23/2020 Corrections Issued DAVID FEILER
Green Building Rough 10/23/2020 Not Ready for Inspection DAVID FEILER
MERV13>=Final 10/23/2020 Approved DAVID FEILER
MERV13>=Rough 10/23/2020 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Not Ready DAVID FEILER
Smoke Detectors 10/23/2020 Approved DAVID FEILER
BUILDING-Rough-Frame 11/9/2020 Approved OSVALDO PARAMO
Final 11/9/2020 Corrections Issued OSVALDO PARAMO
Green Building Final 11/9/2020 Approved OSVALDO PARAMO
Green Building Rough 11/9/2020 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 11/9/2020 SGSOV Approved OSVALDO PARAMO
Final 11/17/2020 Corrections Issued DAVID FEILER
Final 11/24/2020 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 12/7/2020 Approved EUGENE CASSIDY
Final 12/7/2020 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 12/7/2020 Approved EUGENE CASSIDY
PLUMBING-Final 12/7/2020 Approved EUGENE CASSIDY