105 S FAIRFAX AVE 90036

Certificate Information: 105 S FAIRFAX AVE 90036

Application / Permit
20016-20000-15445
Plan Check / Job No.
B20VN08656
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Coffee Shop
Work Description
T.I. & CONVERT OF (E) RESTAURANT INTO A COFFE SHOP (1,276 SF) TO AN (E) APARTMENT BLDG WITH SUBTERRANEAN GARAGE. WORK PER ENGINEER. (SEE COMMENTS).
Permit Issued
Issued on 5/26/2021
Issuing Office
Current Status
CofO Corrected on 1/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/13/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 TROY DEGUZMAN
Corrections Issued 8/4/2020 TROY DEGUZMAN
Quality Review Completed 8/6/2020 CHON CHIO KUO
Building Plans Picked Up 8/7/2020 APPLICANT
Plan Check Approved 5/26/2021 TROY DEGUZMAN
Issued 5/26/2021 APPLICANT
CofO in Progress 12/21/2022 EDWIN GREGORYONA
CofO Issued-Status Void 1/11/2023 TED RIES
Permit Finaled-Status Void 1/11/2023 TED RIES
Re-Activate Permit 1/13/2023 TED RIES
CofO Corrected 1/13/2023 TED RIES
Permit Finaled 1/13/2023 TED RIES

Permit Application Clearance Information

Miscellaneous Cleared 8/11/2020 PABLO ESTRADA
Miscellaneous Cleared 8/11/2020 PABLO ESTRADA
Miscellaneous Cleared 8/11/2020 PABLO ESTRADA
Eng Process Fee Ord 176,300 Cleared 9/28/2020 RENZ SORIANO
Encroachment in public way Cleared 9/29/2020 ELENA LOPEZ
Sewer availability Cleared 10/21/2020 RENZ SORIANO
DAS Clearance Cleared 5/20/2021 TROY DEGUZMAN
Food establishment approval Cleared 5/21/2021 LACDHS APPROVED

Contact Information

Contractor Construction Group Inc A; Lic. No.: 811094-B 6520 PLATT AVE #655      WEST HILLS, CA 91307
Engineer Arsen, Adzhemyan; Lic. No.: C89103 1010 RALEIGH ST   APT # 107    GLENDALE, CA 91205

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 12/20/2021 Not Ready for Inspection JONATHAN QUACH
Wood Frame 12/20/2021 Partial Inspection JONATHAN QUACH
METHANE-Rough 1/5/2022 Approved JONATHAN QUACH
Wood Frame 1/5/2022 Approved JONATHAN QUACH
Drywall Nailing 1/18/2022 Conditional Approval DARRYL ARNOLD
Final 12/13/2022 Not Ready for Inspection ALFREDO LOPEZ
Reinforced Concrete Frame 12/13/2022 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 12/13/2022 Approved ALFREDO LOPEZ
Final 12/20/2022 Conditional Approval EDWIN GREGORYONA