2225 S SUPERIOR AVE 90291
Certificate Information: 2225 S SUPERIOR AVE 90291
- Application / Permit
- 20016-20000-15177
- Plan Check / Job No.
- B20VN08504
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Current Status
- Issued on 9/13/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2020 | RAPHAEL ROSAS |
| Corrections Issued | 7/6/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 7/24/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 9/8/2021 | APPLICANT |
| Issued | 9/13/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2020 | OSCAR GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 8/6/2020 | OSCAR GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2020 | OSCAR GUTIERREZ |
| Sewer availability | Cleared | 5/4/2021 | RAYMOND MUGAMBWA |
Contact Information
| Contractor | Guy Boulanger Construction Company Inc; Lic. No.: 896548-B | 3305 TILDEN AVENUE LOS ANGELES, CA 90034 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/30/2021 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 12/15/2021 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 1/12/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 4/15/2022 | Corrections Issued | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 4/15/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 5/12/2022 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 5/12/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Insulation | 5/12/2022 | Conditional Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 5/12/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 5/27/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 5/27/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 5/27/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/27/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 5/27/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/28/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 6/30/2022 | Approved | DAVID FEILER |
| Green Building Rough | 6/30/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 7/6/2022 | Approved | DAVID FEILER |
| Insulation | 7/6/2022 | Approved | DAVID FEILER |
| Final | 8/31/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 8/31/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/31/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 8/31/2022 | Approved | JESUS RODRIGUEZ |
| Final | 10/11/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Final | 10/11/2022 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Approved | DAVID FEILER |
| Final | 10/20/2022 | Partial Approval | DAVID FEILER |
| Gas Test | 10/20/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 4/4/2024 | Approved | RICHARD STEINBACH |
| HVAC-Final | 4/4/2024 | Approved | RICHARD STEINBACH |
| PLUMBING-Final | 4/4/2024 | Approved | RICHARD STEINBACH |
| Special/Order Compliance | 4/4/2024 | Corrections Issued | RICHARD STEINBACH |