7905-7907 W JAYSEEL ST 91040

Certificate Information: 7905-7907 W JAYSEEL ST 91040

Application / Permit
20016-20000-15129
Plan Check / Job No.
B20VN08480
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 880 SQ. FT. PORTION OF THE (E) SINGLE FAMILY DWELLING INTO A (N) ACCESSORY DWELLING UNIT AND REPLACE ALL WINDOWS SAME SIZE/TYPE. WORK DONE PER WFPP.
Permit Issued
Issued on 8/3/2020
Issuing Office
Current Status
CofO Issued on 2/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 SARKIS HARABEDIAN
Corrections Issued 7/3/2020 SARKIS HARABEDIAN
Plan Check Approved 8/3/2020 SARKIS HARABEDIAN
Issued 8/3/2020 APPLICANT
CofO in Progress 11/13/2020 MATTHEW NELSON
Permit Finaled 2/13/2021 MICHAEL SMITH
CofO Issued 2/13/2021 MICHAEL SMITH
Permit Finaled 2/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/17/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/17/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/9/2020 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 9/9/2020 Corrections Issued MATTHEW NELSON
Green Building Rough 9/9/2020 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 9/9/2020 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 9/9/2020 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 9/10/2020 Not Ready for Inspection DAVID MATSON
HVAC-Rough 9/10/2020 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 9/10/2020 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 9/14/2020 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 9/14/2020 Approved MATTHEW NELSON
Green Building Rough 9/14/2020 Approved MATTHEW NELSON
HVAC-Rough 9/14/2020 Approved MATTHEW NELSON
PLUMBING-Rough 9/14/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 9/16/2020 Approved MATTHEW NELSON
Insulation 9/18/2020 Approved MATTHEW NELSON
Drywall Nailing 9/23/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 9/25/2020 Approved MATTHEW NELSON
ELECTRICAL-Final 10/21/2020 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 10/21/2020 Corrections Issued MATTHEW NELSON
Interior/Exterior Lathing 10/21/2020 Approved MATTHEW NELSON
ELECTRICAL-Final 10/23/2020 Approved MATTHEW NELSON
HVAC-Final 10/23/2020 Approved MATTHEW NELSON
PLUMBING-Final 10/23/2020 Not Ready for Inspection MATTHEW NELSON
Final 10/27/2020 Corrections Issued MATTHEW NELSON
Green Building Final 10/27/2020 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 10/27/2020 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/27/2020 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 10/27/2020 Approved MATTHEW NELSON
Final 11/13/2020 OK to Issue CofO MATTHEW NELSON
Green Building Final 11/13/2020 Approved MATTHEW NELSON
PLUMBING-Final 11/13/2020 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/13/2020 SGSOV Approved MATTHEW NELSON