15528 W TUBA ST 91345

Certificate Information: 15528 W TUBA ST 91345

Application / Permit
20016-20000-14980
Plan Check / Job No.
B20VN08399
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DETACHED GARAGE AND STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 8/22/2024
Issuing Office
Current Status
CofO in Progress on 5/29/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 RARES BODEA
Corrections Issued 7/26/2020 RARES BODEA
Building Plans Picked Up 7/28/2020 APPLICANT
Applicant returned to address corrections 9/22/2020 RARES BODEA
Plan Check Approved 8/22/2024 ALEC MOUSAKHANIAN
Issued 8/22/2024 APPLICANT
CofO in Progress 5/29/2026 JENNIFER RABUCHIN

Permit Application Clearance Information

Address approval Cleared 8/11/2020 GABRIEL ROBLES
Sewer availability Cleared 8/11/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/12/2020 GABRIEL ROBLES
ZA Case Cleared 8/24/2020 HERMINIGILDO AGUSTIN

Contact Information

Contractor Ivy Green Construction; Lic. No.: 1014647-B 16800 DEVONSHIRE ST SUITE 307      GRANADA HILLS, CA 91344
Engineer Valencia,, Byron Steve; Lic. No.: C87372 13719 OXNARD ST 101      VAN NUYS, CA 91401

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/18/2024 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 9/18/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/17/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 12/20/2024 Approved MISAEL ESPARZA
HVAC-Rough 12/20/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 1/27/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 1/29/2025 Approved JENNIFER RABUCHIN
Insulation 2/4/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 3/5/2025 Approved JENNIFER RABUCHIN
Shower Pan 5/9/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/12/2025 Partial Approval MICHAEL CORTEZ
BUILDING-Rough-Frame 12/15/2025 Approved KEVIN BERBERYAN
Final 12/15/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 12/15/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 12/15/2025 Approved KEVIN BERBERYAN
MERV13>=Final 12/15/2025 Approved KEVIN BERBERYAN
MERV13>=Rough 12/15/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/15/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 12/15/2025 Approved KEVIN BERBERYAN
Final 1/16/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/16/2026 Corrections Issued JENNIFER RABUCHIN
Final 5/22/2026 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 5/22/2026 Approved JENNIFER RABUCHIN