10883-10885 N ARLETA AVE 91345
Certificate Information: 10883-10885 N ARLETA AVE 91345
- Application / Permit
- 20016-20000-14863
- Plan Check / Job No.
- B20VN08348
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 18'9" X 26'1" PORTION THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT, CONVERT 8'5" X 6'5" PORTION OF (E) GARAGE TO LAUNDRY ROOM PART OF THE SFD, ALL WORK PER WFPP
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Current Status
- CofO Issued on 9/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2020 | RARES BODEA |
| Corrections Issued | 6/29/2020 | RARES BODEA |
| Building Plans Picked Up | 7/2/2020 | APPLICANT |
| Plan Check Approved | 8/18/2020 | RARES BODEA |
| Issued | 8/19/2020 | APPLICANT |
| CofO in Progress | 8/22/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 9/9/2024 | DANIEL ORRANTE |
| CofO Issued | 9/9/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/3/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/22/2020 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/2/2020 | Partial Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/2/2020 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/4/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/17/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 9/17/2021 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Rough | 9/17/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 4/22/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Gas Test | 5/23/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 5/23/2022 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 5/23/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/29/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 7/29/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/10/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/10/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 2/10/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 2/10/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/10/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/16/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 2/16/2023 | Approved | RAUL OLAGI |
| Insulation | 2/16/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 2/16/2023 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 2/27/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/26/2024 | Approved | JENNIFER RABUCHIN |
| Final | 7/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/26/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/26/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/26/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/26/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/21/2024 | Approved | JENNIFER RABUCHIN |
| Final | 8/21/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 8/21/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/21/2024 | Approved | JENNIFER RABUCHIN |