3517 S MULLDAE AVE 90732
Certificate Information: 3517 S MULLDAE AVE 90732
- Application / Permit
- 20016-20000-14855
- Plan Check / Job No.
- B20VN08343
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL TO (E) SFD AND REMOVE & REPLACE ENTIRE ROOF (ALL EXTERIOR WALLS TO REMAIN). NFPA 13 D FIRE SPRINKLERS REQ'D THROUGHOUT
- Permit Issued
- Issued on 8/10/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 7/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | MARVEL DELACRUZ |
| Corrections Issued | 8/26/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 8/28/2020 | STEVEN KIM |
| Building Plans Picked Up | 9/11/2020 | APPLICANT |
| Applicant returned to address corrections | 4/25/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/23/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/15/2023 | MARVEL DELACRUZ |
| Plan Check Approved | 5/3/2023 | MARVEL DELACRUZ |
| Issued | 8/10/2023 | APPLICANT |
| Permit Finaled | 7/18/2025 | JOSEPH MCGARRY |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 3/31/2022 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 3/31/2022 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/31/2022 | ERIK BEASLEY |
| Grading Pre-Inspection | Cleared | 4/12/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2022 | ERIK BEASLEY |
| Miscellaneous | Cleared | 5/9/2022 | JOSE HERNANDEZ |
| Construction near power lines | Cleared | 6/21/2022 | RIDWAN HARDY |
| Distance to fire station | Cleared | 9/21/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 10/24/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 10/24/2022 | ANA SORIANO |
| ZA Case | Cleared | 12/1/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 2/8/2023 | ANACANY HURTADO |
| Green Code | Cleared | 2/15/2023 | MARVEL DELACRUZ |
Contact Information
| Contractor | Set-Builders; Lic. No.: 1070338-B | 17412 VENTURA BLVD #150 ENCINO, CA 91316 |
| Engineer | Haddad,, Alexander H; Lic. No.: C76351 | 3528 DUNE LN LA VERNE, CA 91750 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 9/20/2023 | Conditional Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 9/21/2023 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 11/16/2023 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 11/16/2023 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Rough | 12/18/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Footing/Foundation/Slab | 12/18/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Rough | 12/18/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 12/18/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 12/21/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Footing/Foundation/Slab | 12/21/2023 | Partial Approval | JAMES CHAVEZ |
| HVAC-Rough | 12/21/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 12/21/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 3/21/2024 | Partial Approval | ANSON MAGLASANG |
| HVAC-Rough | 3/21/2024 | Partial Approval | ANSON MAGLASANG |
| PLUMBING-Rough | 3/21/2024 | Partial Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 4/4/2024 | Partial Approval | ANSON MAGLASANG |
| HVAC-Rough | 4/4/2024 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 4/4/2024 | Approved | ANSON MAGLASANG |
| Deputy Wood Construction | 4/10/2024 | Conditional Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 4/24/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2024 | Corrections Issued | JAMES CHAVEZ |
| Green Building Rough | 4/24/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 5/13/2024 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Rough | 5/13/2024 | Approved | ANSON MAGLASANG |
| Footing/Foundation/Slab | 5/13/2024 | Approved | ANSON MAGLASANG |
| Green Building Rough | 5/13/2024 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 6/7/2024 | Approved | EUGENE CASSIDY |
| Insulation | 6/7/2024 | Approved | EUGENE CASSIDY |
| Insulation | 6/10/2024 | No Access for Inspection | JAMES CHAVEZ |
| Drywall Nailing | 6/28/2024 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 7/23/2024 | Partial Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/27/2024 | Approved | EUGENE CASSIDY |
| Shower Pan | 8/27/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/19/2025 | Approved | JOSEPH MCGARRY |
| Green Building Final | 2/19/2025 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 2/19/2025 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 2/19/2025 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 2/19/2025 | Approved | JOSEPH MCGARRY |
| Final | 3/25/2025 | Conditional Approval | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/25/2025 | SGSOV Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 3/25/2025 | Approved | JOSEPH MCGARRY |
| Final | 7/18/2025 | Permit Finaled | JOSEPH MCGARRY |